Loading...
WA9302A-CS 960312SHIMEK, JACOBS FINKLEA Date: 3/12/96 Is This A y. ary . Uendr.cks Working nay? [Z~'~ [] No Owner: City of Coppell Project Name: Village Parkway Pump Station Addition Construction Contractor: North Texas Municipal Construction Co., Inc Time Allotted: 3 C)0 Used: Number Superintendent: Bill Bigham. Men Working: 5 Hours: 9:00 am to 9:20 am Weather Conditions: Sunny and cool Site Conditions: Clean and well maintained WORK DESCRIPTION I met the new project superintendent, Bill Bigham. He indicated he has not yet met the City's inspector. The existing concrete for the new addition had been removed and disposed of. Excavation for the foundation and grade beams is complete and the existing electric duct bank located. This work was completed two weeks ago and the conflict with the existing duct bank resolved ( see S, J & F's letter dated 3/11/96) The electrical subcontractor, Texsun Electric, was beginning work to relocate the electric service conduit. The concrete for the new conduit location had been sawed and broken. The contractor was waiting for the City to move the sewer truck out of the pump station building so that he could proceed with the concrete removal Several fence extension sections had been fabricated and were on site. They appeared to be of the same general weight, material and dimensions of the existing fence. None had been installed at this time. cc: North Texas Municipal Construction Co.