ST05-02A-CN0150619City of Coppell Engineering Department
Routing Sheet for Approval of Contracts and Agreements
Vendor Name: (-,b '5u)c12tC2S Date: � 7� �I4
Contracted Work/Project: 'Pq1z-1,-L%,4A-/
Explanation: -J�-3
Council Approved: oYesNo If yes, Date: Gt Budget Approved: Yes / No
O New Vendor Fj xlsting Vendor O Renewing Contract
Routing Sequence: Initials Date
1. Employee initiating contract/agreement: hkAr 6'mr>z.ia A U 1'J's-
(Include W-9 & ClQform if vendor is not in system.)
2. Supervisor Authorization:
3. Purchasing Manager/Technician: _
(Signature needed only if vendor is new to system or contract has been changed since last time used)
4. Director of Engineering Authorization: Ken Griffin 3D 15
5. Deputy City Manager Authorization: Mike Land
Comments:
6. City Manager:
Comments:
Clay Phillips_ Com" -// �
7. Originals back to Administrative Manager: Kyra Cody
8. Copy of contract/agreement to Jennifer Miller: YES / NO
CITY OF COPPELL
CHANGE OR EXTRA WORK ORDER
PROJECT: Freeport Parkway ST -05-02A
CONTRACTOR: CD Builders, Inc.
OWNER: City of Coppell
CHANGE ORDER NO.: Three (3) DATE: June 9, 2015
1. This change order provides for adjustment of quantities to correspond with the work completed under the
contract.
2. This change order provide for an additional 90 days of contract time to complete the additional work
Item Description Quantity Unit Unit Price Total
Add: 24A
5' sidewalk 16,000
SF
$4.89
$78,240.00
24B
Barrier free ramp (ADA) 2
EA
$2,468.10
$4,936.20
new 99A
Drilled Shafts - extra depth 1
LS
$26,451.02
$26,451.02
Total Additions $109,627.22
Delete:
Total Deletions $0.00
Total Revision to Contract Amount:
$109L627.22
Original contract amount
$5,675,407.81
Net increase in contract amount
$109,627.22
Previously approved changes
$242,550.44
Revised contract amount
$6,027,585.47
Cumulative increase in TOTAL change order amount (Percentage)
6.2%
Net increase in contract time of completion (This Change Order)
90
CITY OF COPPELL
CHANGE OR EXTRA WORK ORDER
Revised Contract time of completion (Including Previous Changes) 410 calendar days
The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full accord
and satisfaction of all past and future liability originating under any clause in the Contract by reason of this
Reco ewe l-1 y CityEngin er Date
�H 6; k C��L� /
Agreed to by Contractor Date
0-7.021/6
Accep by City Date