ST0301C- LR150618 (3)V • GEOTECHNICAL ENGINEERING
• ENVIRONMENTAL CONSULTING GEE Consultants,E Inc.
LEJ • CONSTRUCTION MATERIALS TESTING
10046 Monroe Drive Dallas, Texas 75229 • (214) 352-5433 Fax (214) 352-6972
REINFORCING STEEL PLACEMENT
Report Date: June 18, 2015 Test Date: June 16, 2015
Client: City of Coppell General Report No.: 3
Project Bethel and Coppell Rd. Paving & Utility Impr. Project No.: 214-0140
Identification Reinforcing Steel Observation
Method of Test Visual Observation Page 1 of 1
Results
On June 16, 2015 reinforcing steel was observed at the following locations:
1) Box Culvert Walls (Two Northern Most Walls)
The following discrepancies were noted and called to the attention of Walter and Zepriano, representatives of Tesio
Paving,
1) Add verticle "Z" bar to meet 8" max spacing requirement.
2) Fix spacing between rebar and forms with chairs to meet 2" cover requirement.
The above discrepancies were corrected as noted.
Technician: BT
Note: Sections of wall were covered by forms prior to arrival.
cc: Mr. George Marshall - via: GMarshall@coppelltx.gov
Mr. Rick Odell - via: Rodell@coppelltx.gov
GEE Consultants, Inc Reviewed b TBPE Firm: F-3212 Y�
All letters and reports are For the exclusive use of the client to whom they are addressed and shall not be reproduced without the full approval of GEE Consultants Inc The use of
our name must receive our prior written approval. Our letters and reports apply only to the sample tested and/or observed and are not necessarily indicative of the quantities of apparently
identical or similar products.