WA1005- CS120214
PROJECT NO.: CPL11254 DATE: 2/14/2012
PROJECT: Water, Wastewater and Roadway Impact Fee Update
TO: Ken Griffin, George Marshall
FROM: Jessica Brown
CC: Tricia Hatley, Jessica Vassar, Brandon Huxford
PROJECT UPDATES
Final Draft Report delivered February 9, 2012
Draft CIAC Presentation delivered February 9, 2012
Meeting to review CIAC Presentation February 14, 2012
UPCOMING TASKS AND DELIVERABLES
CIAC Meeting on February 16, 2012
Deliver Final Water, Wastewater and Roadway Impact Fee Report
Council Resolution Public Hearing on February 28, 2012
Final Impact Fee Report available to Public on March 2, 2012
Submit Advertising for Public Hearing on March 9, 2012
Public Hearing on April 10, 2012
PROJECT SCHEDULE
Project is on schedule
STATUS REPORT