WA1005- CS111124 (3)
R/W width (ft) 110 street length (ft) 3400 paving width (ft) 66 avg. cut (ft) 2 sidewalk (ft) 5 R/W needed (SF) 374,000 ,) o S V?- Freeport Parkway Sandy Lake to SH 121 $2,225,901 Right of way 374000 Ouanity Cost Total Excavation (CY) 27704 $10.0 $277,037 Stabilized subgrade (SY) 26444 $2.5 $66,111 Lime (tons) 595 $100.0 $59,500 Concrete paving (SY) 24933 $30.0 $748,000 Sidewalk (SF) 34000 $4.0 $136,000 $1,286,648 Mobilization & R/W prep. 8% - $102,932 Drainage 30% - $385,994 Incidentals 35% $450,327 $2,225,901 Right of way 374000 $4.0 $1,496,000 Engineering Design - - $400,000 Geotechnical - $35,000 $4,156,901 Contingency 15% $623,535 Total Cost $4,780,436 NCTCOG participation per 02/05 MOU $3,640,000 Total City Cost $1,140,436 Budget # — $1,200,000 rev. 1/31/05 Freeport sandy lake to sh121 cipAs 1/31/05