WA1005- CS111005
CIP Projects Status
Project #RoadwayFromToStatusCost
1Sandy Lake RoadCity Limit (west)Coppell RoadCompleted$ 3,800,263.33
Estimate - $8,500,000 (split into 2 phases)
2Sandy Lake RoadCoppell RoadDenton Tap RoadCIP
5Royal LaneSandy Lake RoadExtend SouthPart of ST99-02 W. Sandy Lake Road +/-1350' Completed
Estimate - $8,370,421
6Freeport PkwySH 121Sandy Lake RoadCIP
Estimate - $5,150,000
7Freeport PkwyRuby RoadSandy Lake RoadCIP
9Bethel RoadCity Limit (west)Freeport PkwyCompleted$ 7,280,320.90
10Royal LaneIH 635Bethel Road??
11Southwestern BlvdCoppell RoadDenton Tap RoadCompleted$ 1,204,348.91
13Macarthur BlvdBethel School RoadBelt Line RoadCompleted$ 325,393.65
?'s
What about added capacity for Bethel Road at Denton Tap?
We are adding traffic signal to MacArthur & Deforest along with additional turn lane on westbound Deforest.
Why are you not including any of the Coppell Road projects?
CIP Projects Status
Notes
Estimate - $8,500,000 (split into 2 phases)
Meeting notes say complete - don't have estimate
(City Responsible for 20%)
(City Responsible for 20%)
added one southbound lane - Nothing done or any plans in the works
added one southbound lane - is cost provided for one lane? - Yes, actual construction cost.
We are adding traffic signal to MacArthur & Deforest along with additional turn lane on westbound Deforest.