RE coppellSupposed to have an answer today From: Mark Person [mailto:MarkP@gibsonassoc.net] Sent: Wednesday, May 16, 2012 9:25 AM To: Marty Murphy Subject: FW: coppell Marty -- any response from the city or the eng. on the RFI we need to be able to pour the footings next week to meet your schedule. ________________________________ From: Mark Person Sent: Friday, May 11, 2012 7:35 AM To: 'Marty Murphy' Subject: FW: coppell ________________________________ From: Curt Hanson [mailto:chanson@iowabridge.com] Sent: Friday, May 11, 2012 7:25 AM To: Mark Person Subject: Re: coppell RFI- Please provide revised dimension of rail footing for 411MOD rail utilizing existing headwall and wingwall steel in lieu of deck bolts as discussed at our site meeting. Also include revised final top of footing elevations. Verify 411MOD to be built per plan. All information is necessary to order and fabricate steel necessary to proceed.