Phase II completionPhase two was started on 4/10/12 and two way traffic was opened on 6/8/12. The maximum time for full bonus was 48 days which would have been on 6/21/12. JRJ should have acquired a full bonus on 48 days based on these dates above. Marty JRJ Paving, LP 1805 Royal Lane, Ste. 107 Dallas, TX. 75229 214-466-8340