Re COR 2R raise pad grade blocks f&g 2-15-12Marty, Comparing the two change order letters below, I see only a 91CY difference in your estimated quantity of on-site material to be used in this effort between the 1/13 letter and the 2/15 letter. It also seems to me that pay item 107 Embankment (on site) should apply to the 3,861CY of material to be moved from one location on site to another. Using that item, and the contract unit price of $3.46, it seems that item 1 in your request should be reduced to $13,359.06. We understand that time is of the essence in reaching an agreement here, so I have taken the liberty of preparing a change order document reflecting the above change. I have also consolidated the grading to one line item, and reduced the cost to an amount that is agreeable to the city and the developer. If you are in agreement with this proposed change order, please sign and return three copies. If you wish to discuss this change further, I would be happy to facilitate a meeting between JRJ, city staff, and the developer. Thanks, Keith Keith Marvin, P.E. Project Engineer (972) 304-3681 >>> "Marty Murphy" <Martym@JRJPaving.com> 2/15/2012 10:43 AM >>>