Re BETHEL TCPMarty,
JRJ can proceed with the lane closure. We will continue to review the
TCP and make additional suggestions as they arise.
Keith
Keith Marvin, P.E.
Project Engineer
(972) 304-3681
>>> "Marty Murphy" <Martym@JRJPaving.com> 4/9/2012 10:57 AM >>>
Most of the signs are onsite and in place, remainder of the signs will
be ready by noon. Are we good on the revised TCP sent last week? If so
we want to begin closure tomorrow
JRJ Paving, LP
1805 Royal Lane, Ste. 107
Dallas, TX. 75229
214-466-8340