Three transformer padsHi Lonnie:
Hope all is well.
We will be the contracting party for the park job. The agreement with
Oncor and payment will go out today.
The surveyor was provided the first attachment, he will stake the four
corners of the three easement areas and stake the pad elevations
shortly.
The second attachment shows the orientation of the transformers on the
pads, which is critical for us since these lots are so small and
improvements are planned nearby. If there is any reason the orientation
is a problem, we need to address it now as we have restaurants preparing
site plans on both lots presently.
Please prepare an agreement for us at your earliest convenience. The
entity is:
Main Street Coppell, Ltd.
4956 N. O’Connor Road
Irving, Texas 75062
Thanks,
Gregory K. Yancey
Provident Company, Inc.
PO Box 1790
Coppell, TX 75019
V (214) 215-9400
F (214) 276-1709
gregyancey@verizon.net <mailto:gregyancey@verizon.net>
From: Mike Glenn [mailto:cmglenn@glennengineering.com]
Sent: Tuesday, July 02, 2013 11:16 PM
To: surveygroup@att.net
Cc: Greg Yancey
Subject: RE: New E-mail
Rodney, here are the 3 transformers that we need you to stake. Place a
stake at each corner of the 15 x 15 pad and set a grade stake with the
elevation shown. Make sure it is 6-8 inches above the existing grade.
If something looks funny, call me.
Mike Glenn, P.E.
Glenn Engineering Corp.
TBPE Firm F-303
HUB #1752575193300/469711
105 Decker Court, Suite 910
Irving, Texas 75062
972-717-5151(o)
972-672-2450(m)