RE Tidbits 07 27 12 - Project Update DFW Airport Noise Report Upcoming EventsThe architect has agreed that the construction documents will be
complete in August, with bidding to commence after the necessary city
approvals. However, he has been less than forthcoming with review plans
and requested correspondence during the design phase. No firm date has
yet been established for bidding.
From: Keith Marvin
Sent: Monday, July 30, 2012 8:15 AM
To: Brad Reid
Cc: Leslie Henderson; Clay Phillips; Mario Canizares; Mike Land; Debbie
Cravey; Kenneth Griffin
Subject: RE: Tidbits 07.27.12 - Project Update, DFW Airport Noise
Report, Upcoming Events
Brad,
This was inadvertently sent to me. Can you respond to Debbie?
Thanks.
Keith
Keith Marvin, P.E.
City of Coppell
972-304-3681
From: Debbie Cravey
Sent: Monday, July 30, 2012 8:04 AM
To: Keith Marvin
Cc: Leslie Henderson; Clay Phillips; Mario Canizares; Mike Land
Subject: FW: Tidbits 07.27.12 - Project Update, DFW Airport Noise
Report, Upcoming Events
Keith, Billy Faught is asking what the schedule is for design and
bidding for the pavilion in Old Town?
Debbie Cravey
Administrative Asst. to the City Manager
City of Coppell
972-304-3618
dcravey@coppelltx.gov <mailto:dcravey@coppelltx.gov>
<http://www.facebook.com/pages/City-of-Coppell-TX/324357528624>
<http://twitter.com/#!/CityofCoppell>
<http://www.youtube.com/user/CityOfCoppellTX>
<http://coppelltx.gov/ecocoppell>
From: Billy Faught
Sent: Friday, July 27, 2012 9:00 PM
To: Debbie Cravey
Subject: RE: Tidbits 07.27.12 - Project Update, DFW Airport Noise
Report, Upcoming Events
What is the schedule for design and bidding for the pavillion in Old
Town?
Thanks,
Billy
Sent from my Android phone using TouchDown (www.nitrodesk.com
<http://www.nitrodesk.com> )
-----Original Message-----
From: Debbie Cravey [DCravey@coppelltx.gov]
Received: Friday, 27 Jul 2012, 4:34pm
To: Christel Pettinos [CPettinos@coppelltx.gov]; Clay Phillips
[CPhillips@coppelltx.gov]; Debbie Cravey [DCravey@coppelltx.gov];
Directors [Directors@coppell.city]; Mario Canizares
[MCanizares@coppelltx.gov]; Mike Land [MLand@coppelltx.gov]; Mindi
Hurley [MHurley@coppelltx.gov]; Scarlett Hovland
[SHovland@coppelltx.gov]; Sharon Logan [SLogan@coppelltx.gov]; Tidbits
[Tidbits@coppelltx.gov]
Subject: Tidbits 07.27.12 - Project Update, DFW Airport Noise Report,
Upcoming Events
1. Keith Marvin in our Engineering Department has prepared a project
status update. The report is attached for your review. Please feel
free to call Keith if you have any specific questions regarding these
projects.
2. Please note there are two complaints in the DFW Airport Noise
Report for this reporting period.
3. Attached is the list of upcoming activities and associated dates
for items that you either need to have on your calendar or items that
you may be interested in attending.