Re BETHEL TCP (2)Thanks Sent from my iPhone Marty Murphy, Business Manager On Apr 9, 2012, at 11:11 AM, "Keith Marvin" <kmarvin@coppelltx.gov <mailto:kmarvin@coppelltx.gov> > wrote: Marty, JRJ can proceed with the lane closure. We will continue to review the TCP and make additional suggestions as they arise. Keith Keith Marvin, P.E. Project Engineer (972) 304-3681 >>> "Marty Murphy" <Martym@JRJPaving.com <mailto:Martym@JRJPaving.com> > 4/9/2012 10:57 AM >>> Most of the signs are onsite and in place, remainder of the signs will be ready by noon. Are we good on the revised TCP sent last week? If so we want to begin closure tomorrow JRJ Paving, LP 1805 Royal Lane, Ste. 107 Dallas, TX. 75229 214-466-8340