Re Proposed Change Order No 1 (4)Yes today
Sent from my iPhone
Marty Murphy,
Business Manager
On Apr 19, 2012, at 4:06 PM, "Keith Marvin" <KMARVIN@coppelltx.gov> wrote:
> Have you completed the re-grading of the lots?
>
>
> -----Original Message-----
> From: "Marty Murphy" <Martym@JRJPaving.com>
> To: Keith Marvin <KMARVIN@coppelltx.gov>
>
> Sent: 4/19/2012 3:59:13 PM
> Subject: RE: Proposed Change Order No. 1
>
> Phase three was completed on 4/13/12 after re-inspection by water department, this would 49 days before 6/1/12, do you agree?
>
>
>
> From: Keith Marvin [mailto:kmarvin@coppelltx.gov]
> Sent: Thursday, December 01, 2011 10:58 AM
> To: Marty Murphy
> Cc: Leslie Henderson; Richard Odell
> Subject: RE: Proposed Change Order No. 1
>
>
>
> Marty,
>
>
>
> Based on your request, I have modified the attached Change Order No. 1. We increased the Phase II time to 120 days. In doing so, we reduced the incentive amount from $3,000/day to
$2,000/day. This exceeds the original contract amount for time and incentive.
>
>
>
> If you are agreeable with this change order, please print and sign two copies and send them to us for execution. This will make the change order we take to City Council on 12/13 CO
#2. We will be recommending the re-route option as it will provide more cover over the top of the 16" water line. I will work up the preliminary Change Order and send it to you for
review.
>
>
>
> Thanks,
>
>
>
> Keith
>
>
>
>
>
>
>
> Keith Marvin, P.E.
> Project Engineer
> (972) 304-3681
>
>>>> "Marty Murphy" <Martym@JRJPaving.com> 11/14/2011 3:08 PM >>>
>
> I am good with everything you have except the Phase II constraints of the bonus only being achieved if the work is complete in less than 90 days. I don’t think we can open two lanes
in 90 days therefore we would have no chance at any of the bonus. I am good with the 120 days but would like to see us have the opportunity to achieve the bonus if completed in less
than 120 days with the same maximum bonus amount.
>
>
>
> Marty Murphy,
>
> Business Manager
>
>
>
> JRJ Paving, LP
>
> 1805 Royal Lane, Ste. 107
>
> Dallas, TX. 75229
>
> 214-466-8340
>
> 214-466-8354 Fax
>
>
>
> From: Keith Marvin [mailto:kmarvin@coppelltx.gov]
> Sent: Thursday, November 10, 2011 5:16 PM
> To: Marty Murphy
> Subject: Proposed Change Order No. 1
>
>
>
> Marty,
>
>
>
> Look this over and let me know what you think.
>
>
>
> Keith
>
>
>
>
>
> Keith Marvin, P.E.
> Project Engineer
> (972) 304-3681
>
>