WA8801-CS 890905GINN, INC. CONSULTING ENGINEERS September 5, 1989 Mr. Jimmy McLean McLean Construction, Inc. P.O. Box 10759 Killeen, TX 76547 Re: 24" Crosstown Waterline Coppell, TX Certificate of Substantial Completion Dear Mr. McLean: The work to which this Certificate applies has been inspected by authorized representatives of the Engineer and that work is hereby declared to be substantially complete in accordance with the Contract Documents as of August 25, 1989. A tentative list of items to be completed or corrected is attached hereto. This list was prepared based upon a preliminary walk-thru made by our Resident Project Repre ttive, City Personnel and McLean Construction, Inc.fJQl~J~u~2~ 1989. This list may not be all inclusive and the lude an item' on it does not alter the responsibility of the Contractor to complete all 'the work in accordance with the Contract Documents. The items on the tentative list shall be completed or corrected by the Contractor prior to requesting a final walk-thru on the project. This Certificate does not constitute an acceptance of work not in accordance with the Contract Documents, nor is it a release of Contractor's obligation to complete the work in accordance with the Contract Documents. Executed by Engineer on ~~/4~~', 1989. Ginn, Inc. Consulting Engineers By: ~~~ 17103 Preston Road ® Suite 100 ® LB 118 ® Dallas, Texas 75248 ® Phone 214/2484900 Contractor accepts this Certificate of Substantial Completion as of August 25, 1989, on this day of 1989 and agrees to complete and correct the items on the attached tentative list within 30 days of the date of substantial completion above. McLean Construction, Inc. By: Owner accepts the project as substantially complete and this Certificate of Substantial Completion as of August 25, 1989, on this day of , 1989 and will ass~ume full possession of the project. as soon as .all items on the tentative list have been addressed. City of Coppell By: City Engineer Please sign and return all copies to us for further execution and distribution. After execution of this document by the Owner, we will return a copy to you. Should you have any question, please contact us. Sincerely, Gabe Favre CO: Russell Doyle, P.E. Alan Ratliff Mayor and Council H. Wayne Ginn, P.E. Randy Fleming Steve Goram Howard Pafford Richard Diano Frank Trando File 274 enclosures: Ginn, Inc. - punch list items City of Coppell - punch list items Parks Department - punch list items August 30, 1989 24" Crosstown Waterline - Coppell, TX Walk-Through - Punch List Items 10. 11. 12. 13. 14. 15. 16. 17. 18. Remove 24"x24" tee and other fittings in vicinity of Sta. 0+00, Line "A". Provide City with 2 valve operating wrenches. Provide documentation that bacteriological samples have passed tests. Install gravel bedding in bottom of 3/4" corporation stop near Sta. 0+00, Line "A". Paint relocated fire hydrant at Sta. 7+32, Line "A". Clean out silt build up in Grapevine Creek, as discussed. Replace yellow traffic buttons on Southwestern Blvd., west of Belt Line/Denton Tap intersection. Repair or replace electrical pull box, northwest corner of Denton Tap/Belt Line/Southwestern intersection. First inlet east of Gulf Station (Sta. 43+20 ±); need to clean debris from bottom of inlet. Touch up paint at signal pole, NW and SE corner Denton Tap/Belt Line intersection. First ARV east of Gulf Station (Sta. 44+00), remove gravel in bottom in order to operate hand wheel on valve. Provide City with 2 hand wheel operators for air relief valve. Creek bottom, Sta. 80+25, needs to be cleaned up, shaped up and dressed up. ARV, Sta 97+70, is leaking. Need to repair and remove water from vault. ARV, Sta. 110+04, need to pump vault clear of water, make sure valves are open. Repair ball valve handle to operate properly. ARV, Sta. 123+75, needs handwheel on valve to be installed. ARV, Sta. 159+20, repair leak on corporation stop. Line D, Moore Road, south of Carter, need to provide valve nut extension and make sure tapping valve operates properly. 19. 20. 21. 24. 26. 28. 29. 30. 31. 32. 33. 34. 35. 36. Rout and seal concrete, Moore Road south of Carter, where tapping valve installed. Prune deadwood and paint trees in media~'along MacArthur as required and discussed. Remove all dead grass (solid sod) and replace with new sod, fertilize and water as required. Repair any sprinkler heads that were determined to have been disturbed by Contractor, if any. Locate sprinkler heads, using contract plans, mark on curb with paint for Parks Department to repair next week. Traffic buttons north of Sandy Lake need to be removed and replaced properly with correct epoxy. On Line "C" - Parkway Blvd. valves on southeast and southwest corner of intersection of Parkway Blvd. and Denton Tap needs to have valve extensions provided. Backfill HMACP shoulder at Belt Line/Denton Tap northwest radius. Replace 4" yellow buttons, with proper epoxy, on Belt Line east of Gulf Station.. At Starleaf crossover, repair random cracks, south side of median. At Mapleleaf, repair curb at south nose of median opening. Repair curb "ear" at redwood header; correct irregular curb dimensions. Curb at north nose, Mapleleaf crossover, cracking where attached to existing concrete pavement needs to be addressed. Epoxy 4" diameter lane buttons north of Sandy Lake along MacArthur Blvd.; northbound lanes. Skin patch concrete hole at start of reverse curve station of northbound lane, left turn lane. Sweep and clean dirt from brick wheel chair ramps at Village Parkway and MacArthur Blvd. Rout and seal joints on Moore Road, south of Carter Drive. Replace damaged traffic signal pull box at Sandy Lake and Denton Tap. Repaint/touch up signal poles at Denton Tap/Belt Line. Replace 6-8" diameter single reflective yellow traffic buttons on Southwestern Blvd. 37. Hand rake dirt away from traffic controller at Belt Line and Denton Tap Road. Following are separate punch list items prepared by City of Coppell representatives who made the walk-through also. Some may be duplicates of the above list. We have not received written comments from all departments, however it is our understanding that there may be a punch list from the City of Coppell Parks Department forthcoming. When we receive that list, we will forward a copy to you. When all items on all lists have been completed or corrected, please notify this office, in writing, in order that a final walk-through may be made. You may begin processing of final close-out documents as per the contra&t specifications, Section 01700. We will not request City Council approval and acceptance of the project until all punch list items have been addressed or corrected and close-out documents have been submitted. Respectfully submitted: Gabe Favre Ginn, Inc. Consulting Engineers T I I T