Re HWY 121 Upcoming MeetingKeith
I agree with this approach. Originally I was hoping to let our project
by end of July. We need permit from TXDOT in order to start construction
but not necessarily to bid. We are about a week out from being ready to
bid the project.
Chris Schmitt, P.E.
tnp
On Sep 9, 2013, at 8:34 PM, "Keith Marvin" <KMarvin@coppelltx.gov
<mailto:KMarvin@coppelltx.gov> > wrote:
I'm debating whether to go to the next meeting or not.
Atmos is installing their line now. I'm going to have one of
our techs get some shots on it in the morning to see where it is. they
are boring most of it, so all we'll have is where the pits are.
I'm tempted to push through and get in the ground before the
telecoms do...
Keith Marvin
City of Coppell
On Sep 9, 2013, at 11:15 AM, "Casey McBroom"
<CMcBroom@TNPINC.com <mailto:CMcBroom@TNPINC.com> > wrote:
Keith
We are beginning to gear up for the next 121 TxDOT
meeting, and wanted to touch base with you since we have not had much
discussion recently.
Chris was able to get in contact with Charles Martinez
who basically confirmed that he had telecoms at 9’ and 11’ from the
right of way. He also stated that he has not really done much since he
knew this was going to happen, to put words in his mouth. He was not
really impressed with TxDOT’s activities it seemed.
I wanted to see if there was anything we could be doing
in preparation for the next meeting (exhibits, old correspondence,
etc.). Otherwise, we can hold tight until some further decisions are
made. Just let us know.
Thanks.
<image001.jpg>
Casey McBroom, P.E.
Project Engineer