Re ChangesJames,
I'm still a little confused on the bore issue. The pay item for conduit installation does not specify the method of installation, however there are several areas within the plans that
obviously will require the 3" conduit to be placed by "other than open cut". Are you now saying that you expect to be compensated at this new higher price anywhere you end up boring?
Please clarify.
We do want to go ahead and upgrade that one pull box outside the cabinet from the existing type 'A' to a Type 'C'. I'll start a change order, but I prefer to hold it until we get a
little further into the project so we can add any additional items that may come up.
Please call me to discuss the bore issue.
Keith Marvin, P.E.
Project Engineer
(972) 304-3681
>>> James McCorkendale <jmccorkendale@hotmail.com> 5/19/2010 1:18 PM >>>
Keith,
Talked with Morrie about the changes we discussed earlier.
To add a Bore its 22.00 LF and to put in a type C Pull Box is 600.
Thanks
James
_________________________________________________________________
Hotmail is redefining busy with tools for the New Busy. Get more from your inbox.
http://www.windowslive.com/campaign/thenewbusy?ocid=PID28326::T:WLMTAGL:ON:WL:en-US:WM_HMP:042010_2