RE Mockingbird Lane Road Closure (Bethel School to Oriole) (3)Thanks, Keith. We will put this in our PTO newsletter going out this
week.
Have a good day!
Lian Loop @ East
From: Keith Marvin [mailto:KMarvin@coppelltx.gov]
Sent: Tuesday, June 4, 2013 10:11 AM
To: Pam Mitchell; mblevins@coppellisd.com; 'lmacias@coppellisd.com';
jkennedy@coppellisd.com; npye@coppellisd.com;
'lspringer@coppellisd.com'; 'bmcgill@coppellisd.com'; Sid Grant;
tringo@coppellisd.com; mpranske@gmail.com; Lian Loop; mmcvey@satpon.com;
ehatcher@alum.trinity.edu; texasbuckeye@juno.com; Buzz Walker
(buzz_walker@hotmail.com); ldwens@cs.com; Dispatchers; Tim Oates; Eric
Greaser; Mac Tristan; Kevin Richardson; Gregg Loyd; Tony Pletcher; James
Cook
Cc: Matt Atkins (Matt@JVolkConsulting.com); Alberto Samaniego; Shane
Huffman (shuffman_rkm@yahoo.com); Kenneth Griffin; Sharon Logan; Rhonda
Adloo; Glenn Hollowell
Subject: Mockingbird Lane Road Closure (Bethel School to Oriole)
As most of you are aware, we have been working on the reconstruction of
Mockingbird Lane for the last month. The contractor will be completing
their utility tie-ins this week, and will begin the removal and
replacement of the existing pavement on Monday, June 10th.
Beginning on Monday, June 10th traffic on Mockingbird Lane will be
restricted to one-way northbound from Bethel School Road to Oriole Lane.
Please observe all traffic control signage and devices. Detour routes
will be in place and signed for southbound through traffic.
We apologize for the inconvenience this may cause you, however this
will allow us to re-open the road to two-way traffic by the start of
school on August 26th. Should you have any questions about this work,
please feel free to call the construction inspector, Albert Samaniego at
469-576-1458, or I at the contact number below.
Please help us get the word out by forwarding this information to your
friends, neighbors, or co-workers.
Thanks.