Re Spillway (2)Ken, here's what I recall. We, like you, are anxious to get started.
The cad drawings for the channel alignment have been provided by BBCPI which I thought Keith was going to superimpose on your aerial. Was I mistaken on this or do you still need the
line work?
After checking our files, Mike Boyd & Richard Arvizu have previously provided all the wetlands info that we currently have. From those sketches, it does appear that the proposed channel
could possibly touch the wetlands in two distinct spots. However, if John Rutledge is correct about it being okay to dig in a wetlands with a backhoe rather than a dozer, this shouldn't
be an insurmountable problem.
Assuming that you, Dallas and TCEQ are all now okay with your dewatering plan, what will the City of Irving need for their approvals and how quickly do you think the work can proceed?
Bill Walker
> On Feb 10, 2014, at 7:51 PM, "Kenneth Griffin" <KGriffin@coppelltx.gov> wrote:
>
> Bill
>
> From our meeting last week I understood that Binkley-Barfield was going to provide line work so the location of the channel could be shown on an aerial. We don't have to do the exhibit
that way but it was for ease of understanding where the channel was going to go.
>
> There also was discussion about the wetlands and getting information from your consultant on where wetlands were on site.
>
> If something else was discussed after I left someone needs to let me know. Also could someone update me on the accuracy of my comments and where we are on getting information pulled
together so the project can proceed.
>
> Thanks
> Ken
>
> Sent from my iPhone
>
>> On Feb 10, 2014, at 7:29 PM, "Bill Walker" <BWalker@Billingsleyco.com> wrote:
>>
>> I'm confused ... what exactly are you needing from us? (see Clay's & Lucy's comments below)
>>
>> As we stated in our meeting, there isn't a channel design at this stage other than alignment which was provided to you awhile back.
>>
>> Let's talk in the morning.
>>
>> Bill Walker
>>
>> Begin forwarded message:
>>
>> From: Lucy Billingsley <LBillingsley@Billingsleyco.com<mailto:LBillingsley@Billingsleyco.com>>
>> Date: February 10, 2014 at 6:53:20 PM CST
>> To: Bill Walker <BWalker@Billingsleyco.com<mailto:BWalker@Billingsleyco.com>>
>> Cc: Henry Billingsley <Hbillingsley@Billingsleyco.com<mailto:Hbillingsley@Billingsleyco.com>>
>> Subject: Spillway
>>
>> Sorry I have gotten back earlier.
>> Clay said that they are waiting on Binkley Barclay and Freese and Nichols to agree on a plan.
>> Apparently Binkley is making the submission to Freese. Can you let me know when they have given the plan to Freese?
>> He expects that they will start immediately after receiving the plan.
>>
>> [Copy of lb.jpg]
>> Lucy Billingsley
>> Partner
>>
>> Billingsley Company | One Arts Plaza | 1722 Routh Street | Suite 1313 | Dallas, TX 75201
>> Direct: 214.270.2222 | www.billingsleyco.com<http://www.billingsleyco.com/> | lbillingsley@billingsleyco.com<mailto:lbillingsley@billingsleyco.com>
>>
>> <image001.jpg>