RE North Lake (4)Bill,
We’re resubmitting to TCEQ in response to their comments this week and
so their approval will not control the schedule. We will also submit
that corrected set of plans and specs to Dallas this week. I don’t know
how long their review takes.
Whenever the City is comfortable advertising, our schedule currently
runs like this:
* 2 months advertise and award to NTP
* 2 months to lower lake to 485 – mostly excavation work
performed
* 4 months to lower lake to 478 – construction of conduit and
intake and the bulk of the work
* 1 min. to 3 max. month delay in contract – was set for y’all
to do plantings with the lake maintained at 478
* 1 month to complete and clean up. Lake will start rising as
dictated by inflows.
How does that fir with your plans?
Thanks
JLR
John L. Rutledge, P.E.
Freese and Nichols, Inc.
4055 International Plaza St 200
Fort Worth, TX 76109
817-735-7284
jlr@freese.com <mailto:jlr@freese.com>
From: Bill Walker [mailto:BWalker@Billingsleyco.com]
Sent: Tuesday, April 30, 2013 10:39 AM
To: 'Kenneth Griffin'; John Rutledge; 'Roy Wilshire P. E. LEED AP
(ROY.WILSHIRE@kimley-horn.com)'
Cc: 'Keith Marvin'
Subject: RE: North Lake
Ken,
Roy concurs that Steve is the correct person. Have you had any
additional feedback from TCEQ?
We still need to firm up your anticipated schedule. You can always
leave the start date open and describe the subsequent steps in + days …
For example:
___(actual date to be filled in when it occurs)___ - Coppell takes
ownership of the land
+ 3 days - Formal submittals to TCEQ & Dallas
+ 30 days - _________________________
+ 90 days - _________________________
________________ - Final completion
At this point, even your best guess would be helpful so that everyone
can begin to plan their work.
Thanks,
Bill Walker, PE
Senior Vice President Development
One Arts Plaza | 1722 Routh Street, Suite 1313
Dallas, Texas 75201 | D 214-270-0983 M 214-577-2283
<http://www.billingsleyco.com/>
We Partner in Creating Life—Enhancing Communities
________________________________
The information contained in this transmission may be privileged and
confidential and is intended only for the use of the
person(s) named above. If you are not the intended recipient, or an
employee or agent responsible for delivering this message to
the intended recipient, any review, dissemination, distribution or
duplication of this communication is strictly prohibited.
From: Bill Walker
Sent: Monday, April 29, 2013 4:22 PM
To: 'Kenneth Griffin'; John Rutledge; Roy Wilshire P. E. LEED AP
(ROY.WILSHIRE@kimley-horn.com <mailto:ROY.WILSHIRE@kimley-horn.com> )
Cc: Keith Marvin
Subject: RE: North Lake
My first thought would be Steve Parker. He’s been handling the
CLOMR/LOMR process.
Roy, am I correct on this?
Bill Walker, PE
Senior Vice President Development
One Arts Plaza | 1722 Routh Street, Suite 1313
Dallas, Texas 75201 | D 214-270-0983 M 214-577-2283
<http://www.billingsleyco.com/>
We Partner in Creating Life—Enhancing Communities
________________________________
The information contained in this transmission may be privileged and
confidential and is intended only for the use of the
person(s) named above. If you are not the intended recipient, or an
employee or agent responsible for delivering this message to
the intended recipient, any review, dissemination, distribution or
duplication of this communication is strictly prohibited.
From: Kenneth Griffin [mailto:KGriffin@coppelltx.gov]
Sent: Monday, April 29, 2013 4:16 PM
To: John Rutledge
Cc: Bill Walker; Keith Marvin
Subject: RE: North Lake
John
Our attorney stopped by today and said that there were still some final
issues, so we still are not the owners of the dam yet. Our attorney is
hoping for a quick resolution.
I don’t have an answer on the other question concerning who to submit
plans to in Dallas. I haven’t dealt with anybody concerning anything but
the utilities. I’m copying Bill Walker on this email and maybe he has a
contact at Dallas to submit the plans to. If not, then I would assume
we would just follow the normal submittal requirements for Dallas.
Ken Griffin
Please consider the environment before printing this message.
________________________________
This electronic mail message is intended exclusively for the individual
or entity to which it is addressed. This message, together with any
attachment, may contain the sender's organization's confidential and
privileged information. The recipient is hereby notified to treat the
information as confidential and privileged and to not disclose or use
the information except as authorized by sender's organization. Any
unauthorized review, printing, retention, copying, disclosure,
distribution, retransmission, dissemination or other use of, or taking
of any action in reliance upon, this information by persons or entities
other than the intended recipient is prohibited. If you received this
message in error, please immediately contact the sender by reply email
and delete all copies of the material from any computer. Thank you for
your cooperation.
灯牥瑡潩屻尪瑨汭慴ㅧ㘱㰠牢紾桜浴牬晴尠楬敮桜浴牬晴‰屻尪瑨汭慴㑧尠慰ൽ笊⩜桜浴瑬条㔱‶⼼潦瑮紾桜浴牬晴素桜浴牬晴‰屻尪瑨汭慴㑧尠慰筽⩜桜浴瑬条㈷屽瑨汭瑲屦慰絲桜浴牬晴രഊ笊⩜桜浴瑬条㠵㰠戯摯㹹ൽ笊⩜桜浴瑬条′灜牡素屻尪瑨汭慴㉧‷⼼瑨汭紾屻尪瑨汭慴㍧尠慰絽