Pumping Option We have looked at the cost to use a pump to pump the lake water into the 42” pipe and it will cost $205,000 to complete. This will allow us to lower the lake in 50 days while avoiding any conflict with surrounding properties. Archer Western would be willing to pay for $50,000 of this cost. This agreement to assist in the cost is based mainly on coming to a quick resolution that will remove the water in 50 days. We have started our excavation and need a response quickly, so this offer will only be valid as long as we hear back in the next two weeks. So the total needed would be $155,000 to complete this. This would be a one-time lowering so if sometime during the project the lake were to rise, we would have to lower it once the intake structure is complete through Billingsley property. Please let me know something on this soon. Sometime next week, our excavation will drop below 480 and at this point we will not be able to drain through the drainage channel to Grapevine Creek. Michael Suarez Archer Western Contractors Cell (817) 819-2073 msuarez@walshgroup.com <mailto:msuarez@archerwestern.com>