RE Cypress Waters - North Lake Lowering ScheduleGentlemen: Has the 1/6/14 North Lake Dam Schedule been revised based on the approved syphoning process? Please distribute the Revised Schedule this week, or send me a copy if already issued. When & Where will the Lake Lowering Progress Meetings be held? Thanks Steve Jones, AIA Project Manager Billingsley Co. / Cell: 214-676-7451 From: Bill Walker Sent: Monday, February 24, 2014 9:53 AM To: Keith Marvin PE (KMarvin@coppelltx.gov); Michael Suarez (msuarez@walshgroup.com) Cc: Tom Holland; Steve Jones; Lucy Billingsley; Zue Munks; Guy Gregg; Andrew Duggan; Brad Moss PE (brad.moss@kimley-horn.com); Roy Wilshire P. E. LEED AP (ROY.WILSHIRE@kimley-horn.com) Subject: FW: Meeting at 1:30pm today Keith / Michael, We need a new schedule that is consistent with the 3-4 month lake lowering scenario that was shared this past Tuesday. Thanks, Bill