RE North Lake Dam -- DRAFT Addendum #1 (7)It would be helpful since they have to estimate time to pump down to
495. I thought he had a lake gauge to work off of, but I guess not. It
doesn’t not need to be survey quality. Nearest half foot would likely be
sufficient.
Thanks,
John
John Rutledge
Freese and Nichols, Inc.
4055 International plaza, St 200
Fort Worth, TX 76109
(817) 735-7284
jlr@freese.com <mailto:jlr@freese.com>
From: Keith Marvin [mailto:KMarvin@coppelltx.gov]
Sent: Monday, November 11, 2013 12:20 PM
To: John Rutledge; Patrick Miles; Kenneth Griffin
Subject: RE: North Lake Dam -- DRAFT Addendum #1
I’m fine with the non-responsive time.
James does not have an accurate lake level at this time. He says “less
than 500”. His estimate is 498-499.
If we need a better number, I can have someone go out and measure.
Keith
From: John Rutledge [mailto:JLR@freese.com]
Sent: Monday, November 11, 2013 12:00 PM
To: Patrick Miles; Keith Marvin; Kenneth Griffin
Subject: RE: North Lake Dam -- DRAFT Addendum #1
I’ll add the point that this identifies for schedule what was already
in the specs. We had forgotten that there was a limit of 365 days, above
which would be considered non-responsive. Is that sufficient based on
our conversation or do we want to add in the idea that differences in
bid time will be used in the evaluation of the bids. We seemed to be
leaning towards just putting in a maximum time, not realizing that one
was already in there, and not an evaluation criteria, but we can go
either way.
Thanks,
John
John Rutledge
Freese and Nichols, Inc.
4055 International plaza, St 200
Fort Worth, TX 76109
(817) 735-7284
jlr@freese.com <mailto:jlr@freese.com>
From: Patrick Miles
Sent: Monday, November 11, 2013 11:52 AM
To: Keith Marvin (KMarvin@coppelltx.gov <mailto:KMarvin@coppelltx.gov>
); kgriffin@coppelltx.gov <mailto:kgriffin@coppelltx.gov>
Cc: John Rutledge
Subject: North Lake Dam -- DRAFT Addendum #1
All-
See the attached PDF for the first draft of Addendum #1 for the North
Lake Dam project. Also, the bid form has been updated and is included in
this PDF as an attachment to the addendum.
One piece of information that is missing is the current lake elevation
from the day of the site visit. Keith, can you get this information from
James?
Let me know if you have any other questions. Thanks.
Patrick Miles, P.E.
Water Resources
Freese and Nichols, Inc.
4055 International Plaza, Suite 200
Fort Worth, Texas 76109
817-735-7236
817-735-7483 fax
www.freese.com
Please consider the environment before printing this message.
________________________________
This electronic mail message is intended exclusively for the individual
or entity to which it is addressed. This message, together with any
attachment, may contain the sender's organization's confidential and
privileged information. The recipient is hereby notified to treat the
information as confidential and privileged and to not disclose or use
the information except as authorized by sender's organization. Any
unauthorized review, printing, retention, copying, disclosure,
distribution, retransmission, dissemination or other use of, or taking
of any action in reliance upon, this information by persons or entities
other than the intended recipient is prohibited. If you received this
message in error, please immediately contact the sender by reply email
and delete all copies of the material from any computer. Thank you for
your cooperation.