RE Valves at Pump Station (2)We will start pumping sometime on Monday.
From: Glenn Hollowell [mailto:GHollow@coppelltx.gov]
Sent: Friday, April 04, 2014 8:15 AM
To: Suarez, Michael; Keith Marvin
Cc: Billy Williams
Subject: Fwd: Valves at Pump Station
The valves are open. When do you plan to start pumping?
Sent from my iPhone
Begin forwarded message:
From: Keith Marvin <KMarvin@coppelltx.gov
<mailto:KMarvin@coppelltx.gov> >
Date: April 3, 2014 at 6:43:43 PM CDT
To: Glenn Hollowell <GHollow@coppelltx.gov
<mailto:GHollow@coppelltx.gov> >
Subject: Re: Valves at Pump Station
Thank you.
Keith Marvin
City of Coppell
On Apr 3, 2014, at 6:42 PM, "Glenn Hollowell"
<GHollow@coppelltx.gov <mailto:GHollow@coppelltx.gov> > wrote:
I will take care of it.
Sent from my iPhone
On Apr 3, 2014, at 3:51 PM, "Keith Marvin"
<KMarvin@coppelltx.gov <mailto:KMarvin@coppelltx.gov> > wrote:
Can you handle this request please.
Keith Marvin
City of Coppell
Begin forwarded message:
From: "Suarez, Michael"
<msuarez@walshgroup.com <mailto:msuarez@walshgroup.com> >
Date: April 3, 2014 at 3:42:42 PM CDT
To: "kmarvin@coppelltx.gov
<mailto:kmarvin@coppelltx.gov> " <kmarvin@coppelltx.gov
<mailto:kmarvin@coppelltx.gov> >
Subject: Valves at Pump Station
Keith,
Can you get the valves open at the pump
station by Friday afternoon? I cannot locate Glenn’s email to request
it from him.
Michael Suarez
Archer Western Contractors
Cell (817) 819-2073
msuarez@walshgroup.com
<mailto:msuarez@archerwestern.com>