FW Unit A2 Toe wall and rip rapKeith,
Attached is the Executed Change Order #2 for the Unit A2 Toe Wall and
rip rap. Two originals will be sent via post to: City of Coppell, ATTN:
Keith Marvin, 255 Parkway BLVD, Coppell, Texas 75019. Please advise if
the address is incorrect.
Thank you,
Marie Castellon
JDK Associates, Inc.
Contracts Administrator
940-686-6236
940-686-6318
Grace and Peace To You!!
From: Steve Kenney [mailto:steve@jdkassoc.com
<mailto:steve@jdkassoc.com> ]
Sent: Friday, October 25, 2013 8:07 AM
To: Marie Castellon
Subject: Fwd: Unit A2 Toe wall and rip rap
Print
Sent from my iPhone
Begin forwarded message:
From: Keith Marvin <KMarvin@coppelltx.gov
<mailto:KMarvin@coppelltx.gov> >
Date: October 25, 2013 at 8:05:29 AM CDT
To: Steve Kenney <steve@jdkassoc.com <mailto:steve@jdkassoc.com>
>
Cc: Alberto Samaniego <ASamaniego@coppelltx.gov
<mailto:ASamaniego@coppelltx.gov> >, Kyra Cody <KCody@coppelltx.gov
<mailto:KCody@coppelltx.gov> >, John Elias <JElias@coppelltx.gov
<mailto:JElias@coppelltx.gov> >
Subject: RE: Unit A2 Toe wall and rip rap
Steve,
Please review the attached change order number 2. If it looks
good to you, please sign and return 2 originals.
This Change Order is for the full price of the spillway, we can
handle the deduct pricing on the next pay request.
Keith Marvin, P.E.
City of Coppell
972-304-3681
From: Steve Kenney [mailto:steve@jdkassoc.com]
Sent: Thursday, October 24, 2013 2:46 PM
To: Keith Marvin
Subject: Re: Unit A2 Toe wall and rip rap
Ok thanks
Sent from my iPhone
On Oct 24, 2013, at 2:44 PM, Keith Marvin <KMarvin@coppelltx.gov
<mailto:KMarvin@coppelltx.gov> > wrote:
Steve,
Go ahead and proceed with this work. I will prepare the
change order for approval.
Keith Marvin, P.E.
City of Coppell
972-304-3681
From: Steve Kenney [mailto:steve@jdkassoc.com]
Sent: Thursday, October 24, 2013 2:27 PM
To: Keith Marvin; asamaniego@coppelltx.gox
<mailto:asamaniego@coppelltx.gox>
Subject: Unit A2 Toe wall and rip rap
Keith,
We can get the toe wall and rip rap at the spill way do
for:
1. Wall 50’L x 6’T x 1’W
2. Remove and replace Rip rap with existing and
new
3. Rebuild small natural stone wall for access
4. Re grade and clean disturbed areas
$14,000.00
($3580.20)
Total $10,419.80
The credit is for Unit A-1 Line 10 that we charged last
pay period that was not supposed to be charged. This price is based on
an answer today or first in the morning, because if we leave and come
back we will need to include a pump and more man hours to complete the
job.
Thanks
Steve Kenney
JDK Associates, Inc.
President