May 12, 1989
Mr. Gabe Favre
Ginn, Inc.
17103 Preston Road, Suite 100
Dallas, Texas 75248
Re: City of Coppell
24" CrosstownWater Line
Dear Mr. Favre:
With regards to the utility lines in Moore Road being at different
location then anticipated we submit to you a request for the following
changes on Line 'D'.
Delete:
-75' 27" steel Casing Pipe @ 95.00/lf
$7,125.00
($7,125.00)
'145' 6" DR-14 PVC Pipe @20.O0/lf
-10 Conc. PCVP Remove & Replace
@65.00/sy
-30' Bore for 6" Pipe @800.00/LS
-16" Gate Valve w/Box @325.00/ea
-1 Mobilization for Bore Sub-Contractor
original 27" Bore @6.00/LS
-1 Labor to Bore Pilot-Hole on 27" Bore
@400.00/LS
'1 Labor for (4) Bore Pits & Remove
Sprinkler System @800.O0/LS
'1 Labor for backfilling, clean-up and
landscaping @400.00/LS
$2,900.00
650.00
800.00
325.00
600.00
400.00
800.00
400.00
6,875.00
($ 250.00)
This change would reduce'the contract price by $250.00 and basically
entail going South down Moore Road for the tie-in, in lieu of crossing
Moore Road to the East, thus avoiding a conflict with the existing storms
drains, gas line and sewer line.
Sinderely,
McLean Construction, Inc.
JW:sh
Jim Watts