ST0301C- LR160119• GEOTECHNICAL ENGINEERING
• ENVIRONMENTAL CONSULTING
E ( • CONSTRUCTION MATERIALS TESTING
GEE Consultan' Isf
10046 Monroe Drive • Dallas, Texas 75229 • (214) 352-5433 +
Fax (214) 352-6972
REPORT OF CONCRETE MIX OBSERVATION
Report Date: January 19, 2016 Date Concrete Placed:
Client: City of Coppell
Project: Bethel & Coppell Road
Contractor: Tiseo Paving
Concrete Supplier and Plant: Tiseo Paving
Location of Placement: Heath Lane and N. Bound Leave Out
December 17, 2015 Standard 6"xl2" Cylinders
Cylinder Cross-sectional Area: 28.27 Square Inches
Concrete Report No.: 49
Project No.: 215-140
MATERIALS Source / SSD Batch Wts. OBSERVATION DATA
Description (Lbs/CuYd)
Mix Number: :2596
Time Sample Batched:
Cement: 6 Sack
Time Sampled:
Sample Location:
Fly Ash:
12/21/15
Coarse Aggregate:
Truck / Ticket No:
Intermediate Aggregate:
Temperature:
Ambient Range:
Fine Aggregate:
Concrete Range:
Admixtures:
Slump Range (inches):
1
Weather Conditions:
28
Time Started:
2
Time Completed:
Added Water: 0 Gallons
Sample Air Content (%):
Total Cubic Yards Placed:
Specimen Measured
Number Slump (in.)
BCR 227
BCR 228
BCR 229 2.75
BCR 230
BCR 231
Test Methods Utilized
ASTM C-31, C-39, C-143
Age
(Days)
Date
Tested
Total Load
(Lbs.)
Compressive Strength
(Lbs./Sq.In.)
4
12/21/15
126,160
4,460
7
12/24/15
130,500
4,620
28
1/14/16
152,080
5,380
28
1/14/16
152,160
5,380
H
H
7:33 AM
8:00 AM
Beath Ln., W. Bound, 10' E. of
Coppell Rd., 3' S. of N. Curb
*/3592
36 OF
60 OF
2.75
Clear
6:00 AM
11:15 AM
2.8
32
Fracture RegularI Cylinders Made By: RB/JP
(Unless Noted Otherwise)
Remarks and/or Distribution: Truck number is not available
cc: Mr. Rick Odell - City of Coppell via E-mail'. Roden@coppelltx&ov
Mr. Michelle Matunas - City of Coppell via Email: mmatunas(rcoppelltx.gov
Mr. George Marshall - City of Coppell via Email: gmarshall{'7a coppelltx.l;ov
Mr. Robert Caudill - Tiseo Paving via Email: rcaudill(i4tiseopavinQ.com
GEE
_'1217
Remarks
All letters and reports are for the exclusive use of the client to whom they are addressed and shall not be reproduced without the full approval of GEE Consultants, Inc. The use of our name must receive
our prior written approval. Our letters and reports apply only to the sample tested and/or observed and are not necessarily indicative of the quantities of apparently identical or similar products.
-INICAL ENGINEERING
VIRONMENTAL CONSULTING
• CONSTRUCTION MATERIALS TESTING
GEE Consultants, Inc.
10046 Monroe Drive • Dallas, Texas 75229 (214) 352-5433 •
Fax (214) 352-6972
Report Date: January 19, 2016 Date Concrete Placed:
Client: City of Coppell
Project: Bethel & Coppell Road
Contractor: Tiseo Paving
Concrete Supplier and Plant: Tiseo Paving
Location of Placement: Inlet Throat Along N. Bound, S. Coppell Rd.
December 17, 2015 Standard 6"x12" Cylinders
Cylinder Cross-sectional Area: 28.27 Square Inches
Concrete Report No.: 50
Project No.: 215-140
MATERIALS Source; / SSD Batch Wts. OBSERVATION DATA
Description (Lbs/CuYd)
Mix Number: 2596 MACH\H
Time Sample Batched:
Cement: 6 Sack
Time Sampled:
Fly Ash:
Sample Location:
Remarks
Truck / Ticket No:
Coarse Aggregate:
Temperature:
Intermediate Aggregate:
Ambient Range:
Fine Aggregate:
Concrete Range:
Admixtures:
Slump Range (inches):
28
Weather Conditions:
1
Time Started:
2
Time Completed:
2.0
Sample Air Content (%):
Added Water: 0 Gallons
Total Cubic Yards Placed:
Reauired Strength (Lbs./sa.in.):
2:00 PM
2:35 PM
Inlet Throat 60' S. of Heath Lane
197/3631
60 OF
71 OF
2.0
Clear
12:30 PM
4:45 PM
3.3
10
3.600
Specimen
Number
Measured
Slump (in.)
Age
(Days)
Date
Tested
Total Load
(Lbs.)
Compressive Strength
(Lbs./Sq.In.)
Remarks
BCR 232
7
12/24/15
149,940
5,300
BCR 233
28
1/14/16
176,020+
6,230+
2.0
BCR 234
28
1/14/16
177,320+
6,270+
BCR 235
H
H
Test Methods Utilized
Fracture Regular
Cylinders Made By: HP
ASTM C-31, C-39, C-143
(Unless Noted Otherwise)
Remarks and/or Distribution:
cc: Mr. Rick Odell - City of Coppell via E-mail: Roden n,coppelltx.gov
Mr. Michelle Matunas - City of Coppell via Email: mmatunas(a-),coppelltx.gov
Mr. George Marshall - City of Coppell via Email: gmarshallAcoppelitx.gov
Mr. Robert Caudill - Tiseo Paving via Email: rcaudill(iMseopaving.com
Inc. TBPE Firm: F-3212
Reviewed
All letters and reports are for the exclusive use of the client to whom they are addressed and shall not be reproduced without the full approval of GEF Consultants, Inc. The use of our name must receive
our prior written approval. Our letters and reports apply only to the sample tested and/or observed and are not necessarily indicative of the quantities of apparently identical or similar products.
G1 * GEOTECHNICAL ENGINEERING
E I a ENVIRONMENTAL CONSULTING
E I* CONSTRUCTION MATERIALS TESTING
GEE Consultants, Inc.
10046 Monroe Drive • Dallas, Texas 75229 • (214) 352-5433 0 Fax (214) 352-6972
Report Date: January 19, 2016 Date Concrete Placed: December 18, 2015 Standard 6"x12" Cylinders
Client: City of Coppell. Cylinder Cross-sectional Area: 28.27 Square Inches
Project: Bethel & Coppell Road Concrete Report No.: 51
Contractor: Axis Company Project No.: 215-140
Concrete Supplier and Plant: TX1 Operation, LP 141
Location of Placement: Driveway, N. Bound at 512 S. Coppell Rd.
Source / SSD Batch Wts. OBSERVATION DATA
MATERIALS Description (Lbs/CuYd)
Mix Number:
8274
Time Sample Batched:
9:04 AM
6 Sack
Time Sampled:
9:55 AM
Cement:
Sample Location:
Driveway in Front of 512
Fly Ash:
Truck / Ticket No:
*/3113307
Coarse Aggregate:
Temperature:
OF
Ambient Range:
41
Intermediate Aggregate:
Concrete Range:
69 OF
Fine Aggregate:
Slump Range (inches):
4.0
Admixtures:
Weather Conditions:
Clear
Time Started:
9:00 AM
Time Completed:
1:30 PM
2
Sample Air Content
3.4
Added Water:
0 Gallons
Total Cubic Yards Placed:
10
Re wired Strenath (Lbs./sq.in.):
3,600
Specimen Measured
Age Date
Total Load Compressive Strength
Remarks
Number Slump (in.)
(Days) Tested
(Lbs.) (Lbs./Sq.1n.)
BCR 236
3 12/21/15
111,940 3,960
BCR 237
6 12/24/15
130,160 4,600
BCR 238 4.0
28 1/15/16
180,800 6,400
BCR 239
28 1/15/16
177,180 6,270
BCR 240
H H
-
Test Methods
�C-143'
Fracture Regular
Cylinders Made By: HP
Cylinders Mad,
F_
(Unless NotedOtherwise)
ASTM C-31, C-39:' t
Remarks and/or Distribution: Truck number is not available
cc: Mr. Rick Odell - City Of Coppell via E-mail: Bso�dellco �elltx- �Ov
Mr. Michelle Matunas . City of Coppell via Email: mrnatunasAcoppelltx.R
ov
Mr. George Marshall - city of'Coppell via Email: gmarshaIl(&_coI)1)elltx.g'oy
Mr. Robert Caudill - Tisco Paving via Email: rcaudi
GEE Consultants, Inc. T'BPE Firm: F-3212
Reviewed by:
�y are addressed and shall not be reproduced without the full approval of GEE Consultants, Inc. The use of our name must receive
All letters and reports are for the exclusive use of the client to whom th( s
our prior written approval. our letters and re
,ports apply only to the ample tested and/or observed and are not necessarily indicative of the quantities of apparently identical or similar products.
iNICAL ENGINEERING
VIRONMENTAL CONSULTING
* CONSTRUCTION MATERIALS TESTING
GEE Consultants, Inc.
10046 Monroe Drive « Dallas, Texas 75229 0 (214) 352-5433 «Fax (214) 352-6972
Report Date: January 19, 2016 Date Concrete Placed:
Client: City of Coppell
Project: Bethel & Coppell Road
Contractor: Axis
Concrete Supplier and Plant: TX1 Operation, LP 141
Location of Placement: Colored Paving at McNear Dr.
December 18, 2015 Standard 6"x12" Cylinders
Cylinder Cross-sectional Area: 28.27 Square Inches
Concrete Report No.: 52
Project No.: 215-140
MATERIALS Source / SSD Batch Wts. OBSERVATION DATA
Description (Lbs/CuYd)
Mix Number: 8274
Time Sample Batched:
Cement: 6 Sack
Time Sampled:
Total Load
(Lbs.)
Sample Location:
Fly Ash:
BCR 241
Coarse Aggregate:
Truck / Ticket No:
Intermediate Aggregate:
Temperature:
3,550
Ambient Range:
Fine Aggregate:
Concrete Range:
Admixtures:
Slump Range (inches):
129,320
Weather Conditions:
Time Started:
2
Time Completed:
Added Water: 0 Gallons
Sample Air Content
5,960
Total Cubic Yards Placed:
BCR 244
Rennired Strength (Lbs./so.in.):
10:43 AM
11:45 AM
Paving, E. Bound at McNear Dr.,
50'E. of S. Coppell Rd.
*/3113739
46 OF
71 OF
4.75
Clear
9:00 AM
1:30 PM
4.0
10
3,600
Specimen
Number
Measured
Slump (in.)
Age
(Days)
Date
Tested
Total Load
(Lbs.)
Compressive Strength
(Lbs./Sq.1n.)
Remarks
BCR 241
3
12/21/15
100,360
3,550
BCR 242
6
12/24/15
129,320
4,570
BCR 243
4.75
28
1/15/16
168,480
5,960
BCR 244
28
1/15/16
168,000
5,940
BCR 245
H
I H
Test Methods Utilized
Fracture Regular
Cylinders Made By: HP
I
ASTM C-3 1, C-39, C- 143
(Unless Noted Otherwise)
Remarks and/or Distribution: Truck number is not available
cc: Mr. Rick Odell - City of Coppell via E-mail: RodeIl(@,coI)I)elhx.Rov_
Mr. Michelle Matunas - City of Coppell via Email: mrmftunasAcoPPd�1txov
Mr. George Marshall - City of Coppell via Email: wnarshallQcoDvelltx.gov
Mr. Robert Caudill - Tiseo Paving via Email-, rcaudill(&tiseonqyjagsm
GEE Consultants, Inc. TBPE Firm: F-3212 Reviewed by:
All letters and reports are for the exclusive use of the client to whom they are addressed and shall not be reproduced without the full approval of GEE Consultants, Inc. The use of our name must receive
our prior written approval. Out letters and reports apply only to the sample tested and/or observed and are not necessarily indicative of the quantities of apparently identical or similar products,
G1 • GEOTECHNICAL ENGINEERING
• ENVIRONMENTAL CONSULTING
E • CONSTRUCTION MATERIALS TESTING
GEE Consultants, Inc.
10046 Monroe Drive • Dallas, Texas 75229 • (214) 352-5433 • Fax (214) 352-6972
Report Date: January 19, 2016 Date Concrete Placed: December 21, 2015 Standard 6'x12" Cylinders
Client: City of Coppell Cylinder Cross-sectional Area: 28.27 Square Inches
Project: Bethel & Coppell Road Concrete Report No.: 53
Contractor: Axis Contracting, Inc. Project No.: 215-140
Concrete Supplier and Plant: TXI Operation, LP 141
Location of Placement: Driveway, North Bound, S. Coppell Rd.
MATERIALS Source / SSD Batch Wts. OBSERVATION DATA
Description (Lbs/CuYd)
Mix Number: 8274
Time Sample Batched:
Cement: 6 Sack
Time Sampled:
Total Load
(Lbs.)
Sample Location:
Fly Ash:
BCR 246
Coarse Aggregate:
Truck / Ticket No:
Intermediate Aggregate:
Temperature:
4,240
Ambient Range:
Fine Aggregate:
Concrete Range:
Admixtures:
Slump Range (inches):
1
Weather Conditions:
Time Started:.
2
Time Completed:
Added Water: 0 Gallons
Sample Air Content (%):
5,660
Total Cubic Yards Placed:
BCR 249
D_-;-4 4 QtrF—th (I hQ /en in 1
2:28 PM
3:10 PM
Driveway in Front of 556, S.
Coppell Rd.
*/3117506
71 OF
78 OF
3.0
Clear
11:45 AM
4:45 PM
3.0
20
1600
Specimen
Number
Measured
Slump (in.)
Age
(Days)
Date
Tested
Total Load
(Lbs.)
Compressive Strength
(Lbs./Sq.In.)
Remarks
BCR 246
7
12/28/15
119,900
4,240
BCR 247
28
1/18/16
162,080
5,730
BCR 248
3.0
28
1/18/16
159,960
5,660
BCR 249
H
H
Test Methods Utilized
Fracture Regular
Cylinders Made By: YS
ASTM C-31, C-39, C-143
(Unless Noted Otherwise)
Remarks and/or Distribution: Truck number is not available
cc: Mr. Rick Odell - City of Coppell via E-mail: RodellAcol)Pclltx.gov
Mr. Michelle Matunas - City of Coppell via Email: mmatunasc&,coppelha-gov
Mr. George Marshall - City of Coppell via Email: a arshall(a,coppelltx.gov
Mr. Robert Caudill - Tiseo Paving via Email: reaudill(a),tiseopaving.com
GEE
:F
All letters and reports are for the exclusive use of the client to whom they are addressed and shall not be reproduced without the full approval of GEE Consultants, Inc. The use of our name must receive
our prior written approval. Our letters and reports apply only to the sample tested and/or observed and are not necessarily indicative of the quantities of apparently identical or similar products.
• GEOTECHNICAL ENGINEERING
• ENVIRONMENTAL CONSULTING
E ` • CONSTRUCTION MATERIALS TESTING
GEE Consultants,
10046 Monroe Drive • Dallas, Texas 75229 • (214) 352-5433 • Fax (214) 352-6972
Report Date: January 19, 2016 Date Concrete Placed: December 22, 2015 Standard 6"x12" Cylinders
Client: City Of Coppell Cylinder Cross-sectional Area: 28.27 Square Inches
Project: Bethel & Coppell Road Concrete Report No.: 54
Contractor: Axis Contracting, Inc. Project No.: 215-140
Concrete Supplier and Plant: TXI Operation, LP 141
Location of Placement: Driveway Approach at S. Coppell Rd.
MATERIALS Source / SSD Batch Wts. OBSERVATION DATA
Description (Lbs/CuYd)
Mix Number: 8274
Time Sample Batched:
2:55 PM
Cement:
Time Sampled:
3:36 PM
Remarks
Sample Location:
Driveway Approach at 532/536 S.
Fly Ash:
12/29/15
Coppell Rd.
Coarse Aggregate:
Truck / Ticket No:
0000/3119779
Intermediate Aggregate:
Temperature:
1/19/16
149,700
Ambient Range:
68 of
Fine Aggregate:
Concrete Range:
78 F
Admixtures:
Slump Range (inches):
6.25
1
Weather Conditions:
Clear
H
Time Started:
11:30 AM
2
Time Completed:
4:45 PM
Added Water: 10 Gallons
Sample Air Content (°l°}:
3.8
Fracture Regular
Total Cubic Yards Placed:
30
(Unless Noted Otherwise)
Re.nuired Strength (Lbs./sa.in.):
3.600
Specimen
Number
Measured
Slump (in.)
Age
(Days)
Date
Tested
Total Load
(Lbs.)
Compressive Strength
(Lbs./Sq.ln.)
Remarks
BCR 250
7
12/29/15
117,680
4,160
BCR 251
28
1/19/16
149,700
5,300
BCR 252
6.25
28
1/19/16
151,120
5,350
BCR 253
H
H
Test Methods Utilized
Fracture Regular
Cylinders Made By: YS
ASTM C-31, C-39, C-143
(Unless Noted Otherwise)
Remarks and/or Distribution:
cc: Mr. Rick Odell - City of Coppell via E-mail: Rodelllmcoppelltx-gov
Mr. Michelle Matunas - City of Coppell via Email: mmatunas(iDcoppelltx.aov
Mr. George Marshall - City of Coppell via Email:__aarshall ,coppelltx.Rov
Mr. Robert Caudill - Tiseo Paving via Email: rcaudill(i- iseopavinng com
Inc. T13PE Firm: F
All tetters and reports are for the exclusive use of the client to whom they are addressed and shall not be reproduced without the full approval of GEE Consultants, Inc. The use of our name must receive
our prior written approval. our letters and reports apply only to the sample tested and/or observed and are not necessarily indicative of the quantities of apparently identical or similar products.
GEOTECHNICAL ENGINEERING
• ENVIRONMENTAL CONSULTING
• CONSTRUCTION MATERIALS TESTING
GEE Consultants,
10046 Monroe Drive Dallas, Texas 75229 • (214) 352-5433 * Fax (214) 352-6972
Report Date:
January 19, 2016 Date Concrete Placed: January 12, 2016
Standard 6"x12" Cylinders
Client:
City of Coppell
Cylinder Cross-sectional Area: 28.27 Square Inches
Project:
Bethel & Coppell Road
Concrete Report No.: 59
Contractor:
Axis Contracting, Inc.
3,740
Project No.: 215-140
Concrete Supplier and Plant:
TXI Operation, LP 141
28
2/9/16
Location of Placement:
S. Coppell Rd., E. Side Sidewalk
MATERIALS
Source / SSD Batch Wts.
OBSERVATION DATA
Description (Lbs/CuYd)
BCR 272
Mix Number:
8272
Time Sample Batched:
10:16 AM
Cement:
BCR 273
Time Sampled:
10:47 AM
I H
Sample Location:
Sidewalk at 20'N. of Approach to
Fly Ash:
Fracture Regular
Cylinders Made By: RB
556
Coarse Aggregate:
Truck / Ticket No:
01/3136193
Intermediate Aggregate:
Temperature:
Fine Aggregate:
Ambient Range:
51 OF
Concrete Range:
54 OF
Admixtures:
Slump Range (inches):
3.25
1
Weather Conditions:
Clear
2
Time Started:
8:30 AM
Time Completed:
5:00 PM
Added Water:
0
Sample Air Content (%):
3.25
Total Cubic Yards Placed:
10.0
Required Streneth (Lbs./so.in.):
3.600
Specimen
Number
Measured
Slump (in.)
Age
(Days)
Date
Tested
Total Load
(Lbs.)
Compressive Strength
(Lbs./Sq.1n.)
Remarks
BCR 270
7
1/19/16
105,600
3,740
BCR 271
28
2/9/16
3.25
BCR 272
28
2/9/16
BCR 273
H
I H
Test Methods Utilized
Fracture Regular
Cylinders Made By: RB
ASTM C-31, C-39, C-143
(Unless Noted Otherwise)
Remarks and/or Distribution:
cc: Mr. Rick Odell - City of Coppell via E-mail: Rodcllncot)Pelltx.gov
Mr. Michelle Matunas - City of Coppell via Email: mmatunas a,conyelltx.gov
Mr. George Marshall - City of Coppell via Email: gmarshali(acoppelltx.gov
Mr, Robert Caudill - Tisco Paving via Email: rcaudill(a),tiseopaving_com
Inc.
F-3212
Reviewed by:
All letters and reports are for the exclusive use of the client to whom they are addressed and shall not be reproduced without the full approval of GEE Consultants, Inc. The use of our name must receive
our prior written approval. Our letters and reports apply only to the sample tested and/or observed and are not necessarily indicative of the quantities of apparently identical or similar products.
' • GEOTECHNICAL ENGINEERING
• ENVIRONMENTAL CONSULTING
I • CONSTRUCTION MATERIALS TESTING
i
10046 Monroe Drive • Dallas, Texas 75229 • (214) 352-5433 •
Fax (214) 352-6972
Report Date: January 19, 2016 Date Concrete Placed: January 12, 2016 Standard 6"x12" Cylinders
Client: City of Coppell Cylinder Cross-sectional Area: 28.27 Square Inches
Project: Bethel & Coppell Road Concrete Report No.: 60
Contractor: Tiseo Paving Project No.: 215-140
Concrete Supplier and Plant: Tiseo Paving
Location of Placement: Parking Space at E. Side of S. Coppell Rd. and Intersection of McNear Dr
MATERIALS Source / SSD Batch Wts. OBSERVATION DATA
Description (Lbs/CuYd)
Mix Number:
Cement:
Fly Ash:
Coarse Aggregate:
Intermediate Aggregate:
Fine Aggregate:
Admixtures:
2
Added Water:
2596
Time Sample Batched:
Time Sampled:
Sample Location:
Truck / Ticket No:
Temperature:
Ambient Range:
Concrete Range:
Slump Range (inches):
Weather Conditions:
Time Started:
Time Completed:
Sample Air Content (%):
Total Cubic Yards Placed:
Require Strength Lbs./s .in.
1.28 PM
2:35 PM
Parking Space at E. Side, 50'N. of
Bethel Rd.
*/28536
64 OF
70 OF
2.75
Clear
8:30 AM
5:00 PM
3.75
8.0
3,600
Specimen
Number
Measured
Slump (in.)
Age
(Days)
Date
Tested
Total Load
(Lbs.)
Compressive Strength
(Lbs./Sq.In.)
Remarks
BCR 274
7
1/19/16
151,300
5,350
BCR 275
28
2/9/16
2.75
BCR 276
28
2/9/16
BCR 277
H
H
Test Methods Utilized
Fracture Regular
Cylinders Made By: RB
ASTM C-31, C-39, C-143
(Unless Noted Otherwise)
Remarks and/or Distribution:
cc: Mr. Rick Odell - City of Coppell via E-mail: Rodell(7a,coppelltx.gov
Mr. Michelle Matunas - City of Coppell via Email: mmatunas(`)a,coppelltx.gov
Mr. George Marshall - City of Coppell via Email: gmarshall(a))coppelltx.gov
Mr. Robert Caudill - Tiseo Paving via Email: rcaudill(@tiseopaving.com
Inc.
Firm: F-3212
All letters and reports are for the exclusive use of the client to whom they are addressed and shall not be reproduced without the full approval of GEE Consultants, Inc. The use of our name must receive
our prior written approval. our letters and reports apply only to the sample tested and/or observed and are not necessarily indicative of the quantities of apparently identical or similar products.
G1 * GEOTECHNICAL ENGINEERING
E I* ENVIRONMENTAL CONSULTING
E I* CONSTRUCTION MATERIALS TESTING
GEE Consultants, Inc.
10046 Monroe Drive •
Dallas, Texas 75229 (214) 352-5433 Fax (214) 352-6972
Report Date: January 19, 2016 Date Concrete Placed: January 14, 2016 Standard 6"xl2" Cylinders
Client: City of Coppell Cylinder Cross-sectional Area: 28.27 Square Inches
Project: Bethel & Coppell Road Concrete Report No.: 61
Contractor: Axis Contracting, Inc. Project No.: 215-140
Concrete Supplier and Plant: TXI Operation, LP 141
Location of Placement: Stamped Concrete Paving, W. Bound, McNear Dr., 30' E. of S. Coppell Rd.
MATERIALS Source / SSD Batch Wts. OBSERVATION DATA
Description (Lbs/CuYd)
Mix Number:
Cement:
Fly Ash:
Coarse Aggregate:
Intermediate Aggregate:
Fine Aggregate:
Admixtures:
I
2
Added Water:
8274
6 Sack
Time Sample Batched:
Time Sampled:
Sample Location:
Truck / Ticket No:
Temperature:
Ambient Range:
Concrete Range:
Slump Range (inches):
Weather Conditions:
Time Started:
Time Completed:
Sample Air Content (0/o):
Total Cubic Yards Placed:
D- ;—A Qt—cnk (I he len in
10:00 AM
10:40 AM
McNear Dr., 30'E of S. Coppell
Rd.
01/3140699
60 OF
66 OF
4.75
Clear
9:30 AM
1:30 PM
3.4
26.0
'i nnn
Specimen
Number
Measured
Slump (in.)
Age
(Days)
Date
Tested
Total Load
(Lbs.)
Compressive Strength
(Lbs./Sq.1n.)
Remarks
BCR 278
4
1/18/16
106,600
3,770
BCR 279
7
1/21/16
BCR 280
4.75
28
2/11/16
BCR 281
28
2/11/16
BCR 282
H
H
Test Methods Utilized
Fracture Regular
Cylinders Made By: HP
ASTM C-31, C-39, C-143
(Unless Noted Otherwise)
Remarks and/or Distribution:
cc: Mr. Rick Odell - City of Coppell via E-mail: Rodellacotmelltx.goy
Mr. Michelle Matunas - City of Coppell via Email: trunatunasacoppelltmov
Mr. George Marshall - City of Coppell via Email: gmarshaIlacoi)Pelltx-gov
Mr. Robert Caudill - Tiseo Paving via Email: roaudill(a)tiseopaving.com
Firm• F
kwhE %-onsultaZIL59 111U. .. . — — I
All letters and reports are for the exclusive use of the client to whom they are addressed and shall not be reproduced without the full approval of GEE Consultants, Inc. The use of our name must receive
our prior written approval. Our letters and reports apply only to the sample tested and/or observed and are not necessarily indicative of the quantities of apparently identical or similar products.