Fairfield- PT151110�COP I PELL
v�,•r `
N A 4
CONSTRUCTION DEVELOPMENT PERMIT APPLICATION
Name of Applicant Northpoint Construction, LLC Date Submitted 11/10/15
Address of Applicant F8530 Esters Blvd., Irving, TX 75063
Phone Number 214-614-6034 Fax Number 214-614-6035
Location of Construction (address, if available): 1150 Northpoint Drive, Coppell, TX 75019
Subdivision Section # Block # Lot #
OR Survey/Abstract # J. Gibson Survey Abst. 1716 Acreage 2.074 7_71
Location description (attach vicinity map): Corner of Northpoint Dr. and SH121 Service Road
1. Type of proposed construction or development:
(., Residential ( Alteration of a natural waterway drainage course
re, Non -Residential C'! Other (describe & attach drawing or sketch)
(7 Placement of Fill (in right-of-way or on private property)
2. Description of Construction Permit requested:
❑X Paving
❑X Sidewalk
❑X
Drive Approach
❑X
Excavation
❑X
Fire Lane
❑
Bridge
❑X
Median or Landscape
X❑
Water Main
X❑
R.C.P.
XQ
Sanitary Sewer Main
❑
Flume
X❑
Inlet
❑ Box Culvert
❑ Rip Rap
❑ Fill Area
❑ Drainage Channel Excavation
❑ Slope Protection/Retaining Wall
❑X Parking Lot
Provide an attachment containing the name and 24 -hr. contact phone number
of supervisor(s) for every contractor working under this general permit.
3.All construction shall be in compliance with, but not limited to, the City of Coppell Subdivision
Ordinance, Standard Construction Details, Streetscape Plan and approved plans. The
contractors shall adhere to the City's Erosion Control & Sedimentation Ordinance.
4.Applicant shall provide a copy of approved plans, specifications and the related cost estimate or
contract for the purpose of permit fee calculation verification.
CONSTRUCTION DEVELOPMENT PERMIT APPLICATION
Page 2
5.A Construction Inspection Permit Fee shall be paid prior to beginning work, in accordance with
the City of Coppell Fee Ordinance. See Page 3 for calculation formula.
Amount Due: $10 614. 5 5 Date Paid: 11 / 11 / 15
NOTE: A separate excavation permit is required anytime pavement is cut or when there is work in the
right-of-way not approved by the City Engineer.
➢Any work requiring closure of a lane of traffic, street, or alley must be approved in
advance by the Engineering Dept., with notification to the following prior to
closure:
Police Department @ 972-304-3600 Street Department @ 972-462-5150
Fire Department @ 972-304-3512 Engineering Dept. Q 972-304-3679
➢Attach barricade plan / trench safety plan of a lane or street closure. (Required)
➢It is a requirement of this permit that As -Built Drawings be turned in at the end of
this project. As-Builts consist of 1 set full size paper copy, 1 set full size mylar and a
CD with Autocad.dwg files.
NOTE: Street closures are allowed from 9:00 a.m. until 3:30 p.m. ONLY
unless otherwise approved by City Engineer.
➢A pre -construction meeting is required prior to beginning work related to this permit.
Contact the inspector assigned to your project to schedule the meeting.
Printing your name indicates your acceptance of the terms and conditions of this form:
214-614-6034
Signature of Applicant Contact Number
01 Pr'kC'-JC fw�'Z/) Fq�T &-,? �p - -7
Signature of Inspector Contact Number
FOR CITY USE ONLY
Is the fill area located in an identified flood hazard area? Q Yes "0
o
If YES, a Floodplain Development Permit is required before any construction can begin.
Is additional information required? l ! Yes t ONo
Are other federal, state, or local permits required? 0 Yes VNo
RMIT APPLICATION APPROVED O PERMIT APPLICATION DENIED
Date
Applicant shall indemnify and forever hold harmless against the City of Coppell each and every claim, demand
or cause of action that may be made or come against it by reason of or if any way arising out of the closure,
blocking, excavating, cutting, tunneling, or other work by the applicant under permit from the City, if such
permit is granted.
T rl 9- C 1 T V 0 )r Page 3
COPPELIL
INSPECTION FEE CALCULATION SHEET
Project Name I Fairfield Inn & Suites Date 11/10/15
As per the City of Coppell Subdivision Regulations, the Developer shall pay 4% of the cost of the items to be permitted and inspected by
the Engineering Department and dedicated to the City. The Developer shall pay 2% of the items to be inspected by the Engineering
Department, but not dedicated to the City such as parking lots, private utilities, private drainage systems and so forth. Inspection fees are
due on or before the date of the Pre -construction Meeting.
In order to verify the inspection fee due, please provide a copy of the development contract(s) and this spreadsheet with
completed calculations to the Engineering Dept. The contract(s) should indicate the cost to construct the following
improvements:
Grand Total (total of 10,614.55
both colored fields)
Submit by E-mailI Print Form
PUBLIC IMPROVEMENTS
CONTRACT AMOUNT
o
X 4/0 =
PRIVATE IMPROVEMENTS
CONTRACT AMOUNT
X2%=
Paving
8,000
320
307,309.39
6,146.19
Water
36,968
1,478.72
43,696
873.93
Sanitary Sewer
5,725
229
7,085
141.7
Storm Sewer
2,370.05
94.8
36,870.94
737.42
Alleys
Sidewalks
9,000
360
12,627
252.54
Other
Total
2,482.52 "
81f3'2'03 'X
r
Grand Total (total of 10,614.55
both colored fields)
Submit by E-mailI Print Form
DATE: 11/10/15
FAIRFIELD INN SUITES
COPPELL, TEXAS
ENGINEER'S ESTIMATE
PROJECT No. 14155
L A,.
ARCHITECTS ENGINEERS I PLANNERS I SURVEYORS
;esfgnrng sc Utons car .0 years
Server & Water
Public Work - Fairfield Inn Co pelt
48" Sanitary Sewer Manhole
$
4,200.00
$
Water - Site (Public)
2 25 LF
8" SDR 35
$
27.00
$
1 2 EA
Connect to existing stub
$
1,000.00
$
2,000.00
2 84 LF
8" C900 DR 14
$
27.00
$
2,268.00
3 1 EA
4" Compound Water Meter Assembly
$
12,000.00
$
12,000,00
4 1 EA
8" Compound Water Meter Assembly
$
12,000.00
$
12;000.00
5 1 EA
8" Gate Valves
$
1,250.00
$
1,250.00
61 2 EA
8"x8" Tee
$
650.00
$
1,300.00
7 1 EA
8"x4" Tapping Saddle
$
850.00
$
850.00
8 1 EA
8"x8" Tapping Saddle
$
850.00
$
850.00
9 1 EA
Fire Hydrant Assembly
$
3,600.00
$
3,600.00
10 84 LF
Trench Safety
$
1.00
$
350.00
11 1 LS
Testing & Erosion Control
$
500.00
$
500.00
12
1 EA
Sub -Total
$
$
36,968.00
Sewer - Site (Public)
I 1 EA
48" Sanitary Sewer Manhole
$
4,200.00
$
4,200.00
2 25 LF
8" SDR 35
$
27.00
$
675.00
3 84 LF
Trench Safety
$
1.00
$
350.00
4 1 LS
Testing & Erosion Control
$
500.00
$
500.00
$
27.00
Sub -Total
17,010.00
I $
5,725.00
Water - Site (Private)
1
2 EA
Connect to existing stub
$
1,000.00
$
2,000.00
2
108 LF
4" C900 DR 14
$
18.00
$
1,944.00
3
48 LF
v C900 DR 14
$
22:00
$
1,056.00
4
630 LF
8" C900 DR 14
$
27.00
$
17,010.00
5
1 EA
8" Gate Valves
$
1,250.00
$
1,250.00
6
1 JEA
6"x8" Tee
$
650.00
$
650.00
7
6 EA
8"x8"Tee
$
650.00
$
3,900.00
8
2 EA
6" 45 Deg Bend
$
500.00
$
1,000.00
9
8 EA
8" 45 Deg Bend
$
500.00
$
4,000.00
10
1 EA
8" 90 Deg Bend
$
500.00
$
500.00
11
2 EA
4" Gate Valves
$
450.00
$
900.00
12
1 EA
6" Gate Valves
$
650.00
$
650.00
13
5 EA
8" Gate Valves
$
850.00
$
4,250.00
14
16 EA
Thrust Blocks
$
175.00
$
2,800.00
15
786 LF
Trench Safety
$
1.00
$
786.00
161
1 LS
ITesting & Erosion Control
$
1,000.00
$
1,000.00
Sub -Total
$
43,696.00
Sewer - Site (Private)
1 I EA
48" Sanitary Sewer Manhole
$
4,200.00
$
4,200.00
2 55 LF
8" SDR 35
$
27.00
$
1,485.00
3 2 EA
6" 45 Deg Bend
$
350.00
$
700.00
4 55 LF
Trench Safety
$
1.00
$
350.00
5 1 LS
Testing & Erosion Control
$
350.00
$
350.00
Sub -Total
$
7,085..00
1JA FARGO 700 Main Avenue Fargo, ND 58103 T 701.293.1350 F 701.293.1353 IJaFargo.com
' N
i
ARCHITECTS ENGINEERS IPIANNERSSURVEYORS
desif01g.5o!u7lons for 60 yerrg
Storm Sewer - Site (Private)
Public Work- Fairfield Inn Coppell
Site Concrete (Public)
11 1 EA
I Street Tie-in/Apron/Pavers $ 8,000.00 $ 8,000.00
1
2 EA
Connect to existing stub
$
1,000.00
$
2,000.00
2
30.99 LF
Overflow Rain Leader - ORL (3")
$
22.00
$
681.78
3
461.75 LF
Overflow Rain Leader - ORL (4")
$
27.00
$
12,467.25
4
38.43 LF
24" RCP
$
35.00
$
1,345.05
5
5 LF
3" HDPE
$
8.00
$
40.00
6
88 LF
4" HDPE
$
9.25
$
814.00
7
80 LF
6" HDPE
$
10.00
$
800.00
8
60 LF
10" HDPE
$
12.00
$
720.00
9
101 LF
12" HDPE
$
14.00
$
1,414.00
10
189.16 LF
15" HDPE
$
18.00
$
3,404.88
11
275.54 LF
21" HDPE
$
21.00
$
5,786.34
12
210.18 LF
24" HDPE
$
25.00
$
5,254.50
13
1540.05 LF
Trench Safety
$
1.00
$
1,540.05
141
1 LS
Testing &Erosion Control
$
1,000.00
$
1,000.00
Sub -Total
$
37,267,85
Site Concrete
Public Work- Fairfield Inn Coppell
Site Concrete (Public)
11 1 EA
I Street Tie-in/Apron/Pavers $ 8,000.00 $ 8,000.00
21 2400 SF
4" City Sidewalk $ 3.75 $ 9,000.00
Sub -Total 17000
Private Work - Fairfield Inn Coppell
Site Concrete (Private)
1
23075.9 SF
7" Cone Paving w/#3 @ 18" OC
$
6.25
$
144,224.56
2
17352.2 SF
6" Cone Paving w/#3 @ 18" OC
$
5.50
$
95,437.10
3
5590.7 SF
5" Cone Paving w/#3@18" OC
$
4.75
$
26,555.83
4
3200.8 SF
4" Concrete Side Walk ( City)
$
3.75
$
12,003.00
5
166.41 SF
4" Concrete Side Walk
$
3.75
$
624.04
6
2739.46 LF
6"x18" Concrete Curb/Gutter
$
15.00
$
41,091.90
7
19432.7 SF
Topsoil Respread behind Curb
$
3.75
$
72,872.51
8
10 SF
Light Pole base
$
350.00
$
3,500.00
Sub -Total
$
239,661.66
LJA FARGO 700 Maln Avenue Fargo, ND 58103Page 2 T 701.293.1350 F 701.293.1353 IjaFargo.com
i ! � a""Kf_a� +�1� I 77 e, ' t /, e , xA Fi � �� � �• ' I `1
I �
a�10-s 1� a f i o
ILI;Ilrmh �5°� — WSandy�akeRd
�.I'•, A ct �� .,,r v., � ,�� I .w,o � ��• k�F,F '+y yj `:"�'� ' �� +' iti
Fairfield Inn and S
;ul,tes-Copp�ell,
i a t
�r
All i
z� � ,a
r i
Ell
� �
e za„5 Goode e'r 'h
Northpoint Construction, LLC
Fairfield Inn & Suites-Coppell, TX
Paving Contractor
Cheyenne Construction Co.
Anthony Burks
214-802-2234
Site Utilites & Site Work
Kencarkey Interests, LLC
Jeremy Henicke
817-905-8115
Landscaping
PR Landscaping
Polo Yanez
972-877-7263