CRDC 14-01CS160227 Project Status Report Project Name: Denton Tap/Sandy Lake, City of Coppell For week of 2/15/2016 -2/27/2016 Key • Drilled remaining foundations along Denton Tap • Prepared rebars, formed and poured concrete for 17 pole foundations accomplishments • Excavated for manhole at Salanta driveway, hauled off dirt and set one 4-way last period manhole • Removed one trench box and adjusted another in preparation for setting second 4- way manhole (at Smashburger) Upcoming tasks Crew No. 1 -Install pipes at Salata and set manhole at Smashburger for this period • Receive 2nd manhole with necks from supplier on Monday • Remove 2nd trench box and adjust remaining trench boxes at Smashburger, Rental will pick up 2 boxes on Monday • Perform excavation at Salata location and prep for 2-6" PVC install to new manhole • Reset trench boxes and set 4-way manhole at Smashburger • Remove and haul off concrete from saw cut • Compact Crew No. 2-Work around intersection(Sandy Lake @ Denton Tap) • Surveyors to stakeout ped poles • Prep area for ground box installation at intersection • Pothole and drill 4 ped pole foundations (2 @ NE and 2 @ SE corner) • Prepare rebars and form work for ped poles • Set new ground boxes at intersection • Pour concrete for ped pole foundations • Run conduits and wires to new ped pole foundations and cabinet • Remove forms • Relocate ped poles on new poles • Install ground box at various locations Crew No. 3-Remove existing pole foundations • Remove two foundations at Denton Tap/Sandy Lake intersection next to the SB LT lane • Remove and clean foundations installed last period • Disconnect circuit to existing street lights foundations • Dig around existing foundations, cut conduit and wiring • Remove foundations and haul off • Start with the two foundation at the Sandy Lake intersection next to the SB LT lane Areas/questions • Awaiting call for when light poles will arrive so we can off load for discussion: • Discuss how to pay for ground boxes relocation at intersection; no pay item in contract • Verify under bridge conduit and hungers • Made contact with Mr. Terry Holmes last week. Will meet with him this week to identify location to haul off dirt • Need contact for Time Warner for ground box • Need to stake light pole along Sandy Lake Rd • Send request for boring crew to work on Saturday 2/20/2016. Need to install conduits by boring in median along Denton Tap median from 121 to Highland Drive,and a small section in the median just south of 121 ATCI CONTRACTING, 1535 SNIDER LANE, LUCAS,TX 75002 1