Fellowship-LR 990706 (2)CONCRETE COMPRE 3IVE STRENGTH TES.
8901 Carpenter Frwy., Suite #100
Dallas, Texas 75247
Report Date
Date of Service: 06/24/1999 Report No.: 9917300 07/06/1999
Client No.: 47677000 Project No.: 94991026
Client: Julian P. Barry General Contractors Project: Fellowship of Las Colinas
Attn: Harold Luedke Phase III - Expansion
6616 Forest Park Road Coppell, Texas
Dallas TX 75235
Services: Obtain samples of fresh concrete at the placement locations, perform required field test and cast
compressive strength samples.
PROJECT DATA
CONTRACTOR: Julian P. Barry CONCRETE CLASS: N/A
CONCRETE SUPPLIER: N/A PLACEMENT DATE: 06/24/1999 RATC}I TIM~: N/A
PLANT: N/A TIYm SAMPLED: N/A aY: Contractor Made
SPECIFICATION REQUIREMENTS WEATHER CONDITIONS: Clear
S~aF~NOTrI: 3000 psi @ 28 Days TEMrERA~JRE (F)- AIR N/A v CONCm~TE: N/A r
SLUMP: 5.0" Max TRUCK NO: N/A TICKET NO: N/A
Am: 3-6% Am COnteNT (%): N/A VmT WEIGHT (pct'): N/A
PLACEMENT LOCATION:
T~ST METHOD: ASTM C- 143 siacwalk
ASTM C-172
ASTM C-39
SAMPLE LOCATION: East side of daycare
REPORT OF TESTS ACCUmJLA~ VA~S: N/^
CYLINDER MEASURED MAXIMUM COMPRESSIVE
MARKED SLUMP DATE AGE LOAD STRENGTH FRACTURE
SET NO. (inches) TESTED (days) (lbs. force) (p~i) TYPE
! 1 N/A 07/01/1999 7 102350 3620
1 2 N/A 07/01/1999 7 96680 3420
Average 3520
1 3 N/A 07/22/1999 28
1 4 N/A 07/22/1999 28
Technician: Ervin Fan'is Started: 10:30am Finished: 12:30pm I-'l~_ Engineering, Inc.
Report Distribution:
(1) Julian P. Barry General Contractors
(1) Urban Architecture Eugene Harbour
(1) City of Grapevine Vice President
(1) City of Coppell
This report is exclusively for the use of the client indicated above and shall not be reproduced except in full without the written approval of HBC Engineering, Inc.