Fellowship-LR 990408 (3)CONCRETE COMPRI _,SIVE STRENGTH TES .'
8901 Carpenter Frwy. Suite #100
Dallas, Texas 75247
Date of Service: 02/10/1999 Report No.: 9904518 Report Date
04/08/1999
Client No.: 47677000 Project No.: 94991026
Client: Julian P. Barry General Contractors Project: Fellowship of Las Colinas
Attn: Harold Luedke Phase III - Expansion
6616 Forest Park Road
Dallas TX 75235 Coppell, Texas
Services: Obtain samples of flesh concrete at the placement locations, perform required field test and cast
compressive strength samples.
PROJECT DATA
CONTRACTOR: Julian P. Barry CONCRETE CLASS: 6 Sack w/air
CONCRETE SVPPLtER: Custom Crete PLACEMENT DATE: 02/09/1999 BATCH T~ME: N/A
PLANT: N/A TIME SAMPLED: 4:30pm ~V: Dean Martin
SPECIFICATION REQUIREMENTS WEATHER CONDITIONS: Sunny and light wind
STRENaTH: 3600 psi @ 28 Days TEMPERATURE (F)- AIR 75 V CONCRETE: 75 F
SLt~n': 4.0" Max TRt~CK NO: 317 TICKET NO: 163690
AIR: 4-6% AIR CONTEWr (%): N/A UNIT WEIG~IT (pcf~: N/A
TEST METHOD: ASTM C-143 PLACEMENT LOCATION:
Inlets 30 & 32
ASTM C-172
ASTM C-39
SAMPLE LOCATION: #30
REPORT OF TESTS ACCUMULATIVE YARDS: N/A
CYLINDER MEASURED MAXIMUM COMPRESSIVE
MARKED SLUMP DATE AGE LOAD STRENGTH FRACTURE
SET NO. (inches) TESTED (days) (lbs. force) (psi) TYPE
1 1 2.00 02/16/1999 7 ! 14700 4060
1 2 2.00 03/09/1999 28 153510 5430
1 3 2.00 03/09/1999 28 145480 5140
Average 5290
1 4 2.00 04/06/1999 56 159880 5650
Batched by truck.
Technician: Dean Martin Started: 2:30pm Finished: 6:00pm ~ E Ina~~no- lC.
Report Distribution:
(1) Julian P. Barry General Contractors
(1) Urban Architecture Eugene Harbour
(I) City of Grapevine Vice President
(I) City of Coppell
This report is exclusively for the use of the client indicated above and shall not be reproduced except in full without the written approval of HBC Engineering, Inc.
01LL Page 1 of 1