ST0301C- LR160309V • GEOTECHNICAL ENGINEERING
E • ENVIRONMENTAL CONSULTING GEE Consultants, Inc.
E • CONSTRUCTION MATERIALS TESTING
10046 Monroe Drive • Dallas, Texas 75229 • (214) 352-5433 +
Fax (214) 352-6972
REINFORCING STEEL PLACEMENT
Report Date: March 9, 2016 Test Date: March 5, 2016
Client: City of Coppell General Report No.: 38
Project Bethel and Coppell Rd. Project No.: 215-0140
Identification Reinforcing Steel Observation
Method of Test Visual Observation
Page 1 of 1
Results
On March 5, 2016 reinforcing steel was observed at the following locations:
1) Bethel Road, East Bound, West of Hearthstone Ln.
The following discrepancies were noted and called to the attention of Jose Villarreal, a representative of Tiseo Paving.
1) Top rebar along curb was absent.
The above discrepancies were corrected as noted..
Technician: HP
cc: Mr. Rick Odell - City of Coppell via E-mail: RodellAcoppelltx.gov
Mr. Michelle Matunas - City of Coppell via Email: mmatunasaa�coppelltx.gov
Mr. George Marshall - City of Coppell via Email: gmarshall(,coppelltx.gov
Mr. Robert Caudill - Tiseo Paving via Email: rcaudill(r7i,tiseopaving.com
GEE Consultants, Inc. TBPE Firm: F-3212 Reviewed by:
All letters and reports are for the exclusive use of the client to whom they are addressed and shall not be reproduced without the full approval of GEE Consultants, Inc. The use of
our name must receive our prior written approval. Our letters and reports apply only to the sample tested and/or observed and are not necessarily indicative of the quantities of apparently
identical or similar products.