Duke Freeport-LR160727 (5)July 27, 2016
Duke Realty
South/West Region
14241 North Dallas Parkway, Suite 1000
ATTN:Mr. Sean Jeanes, P.E. LEED AP
Tohatsu
Location:
Permits:
Dallas, TX 75254
19:6710-A
NEC Bethel Road and Freeport Parkway
Coppell, TX
RE:
ECS Job #
3033 Kellway Drive, Suite 110
Carrollton, TX 75006
(972) 392-3222 [Phone]
(214) 483-9684 [Fax]
ECS Texas, LLP
LETTER OF TRANSMITTAL
Texas Registered Engineering Firm # F-8461
CC:Duke Realty - Todd Henry
Duke Realty - Glen Stevenson
Pacheco Koch Consulting Engineers - Clayton J. Strolle, LEED AP
City of Coppell - Matt Mabry
Weir Bros., Inc. - Mike Weir
Meinhardt & Associates - David Meinhardt
LJB inc - Jim Lintz
ENCL:
We are enclosing:
Materials Engineering Division Reports
For your use
As requested
X
X
X
Field Report # 84 07/25/2016 Loading Dock Footing
Timothy TarbuttonMark R. Zortman, P.E.
Principal Engineer Project ManagerJUL 26 2016
1000.1
This report (and any included attachments) shall not be reproduced, except in full, without the prior written approval of ECS.
ECS Texas, LLP
19:6710-A
84
Tohatsu Monday 07/25/2016
Project No.
Report No.
Day & DateProject
3033 Kellway Drive, Suite 110
Carrollton, TX 75006
(972) 392-3222 [Phone]
(214) 483-9684 [Fax]
FIELD REPORT
2.25
The undersigned arrived on site, as requested, to observe the placement of 29 cubic yards of
3000 psi concrete for Footing at ramp.
The required test limits were determined to be a slump of 3-5 inches, air content of 0-3 %,
batch to placement time of 90 minutes, and concrete temperature range of 50-95 degrees
Fahrenheit.
Concrete observed on this date appeared to be placed in compliance with project specifications
with regard to temperature, slump, air content, and batch to placement time.
One set of five laboratory cured concrete cylinders were cast for compressive strength testing in
our laboratory.
90°/ Sunny
55.00
1.00
0.25
0.00
10:15A 11:15A
Loading Dock Footing
Location
Contractor
On-Site Time
Lab Time
Client
Coppell, TX
Arrival Departure
Summary of Services Performed (field test data, locations, elevations & depths are estimates) & Individuals Contacted.
Duke Realty - Sean Jeanes, P.E. LEED AP
Duke Realty - Sean Jeanes, P.E. LEED AP
Trip Charges*
Remarks
Chargeable Items
Weather
Mileage*
1.00Travel Time*
Total
Time of
Re Obs.Time
* Travel time and mileage will be billed in accordance with the contract.
Tolls/Parking*
Edward SesayBy 1800
1088698
Concrete Summary Report
Project:
Location:
Contractor :
Supplier:
Project No.
Day/Date:
Client:
Weather / Temp:
Page 1
No.Ticket
No.
Truck
No.
CY Concrete
Truck Cum
Batch
Time
Truck Time
Arrive Finish Slump % Air Concrete
Temp.
Water
Added Location and Remarks
Tohatsu 6710-A
NEC Bethel Road and Freeport Parkway
Coppell, - Dallas County - TX 75019-
07/25/2016
Duke Realty
Sunny / 90
Duke Realty
LMC
Mix Designation:5150 Mix Strength:3000 psi Design Strength:3000 psi
B to P
min.
1 7067 63104089 9.0 9.0 09:39 10:05 10:22 *5.00 1.20(P)8643
2 7025 63104091 9.0 18.0 09:52 10:22 10:30 38
3 0275 63104092 11.0 29.0 09:58 10:30 10:38 40
* Location:By:Edward SesayFooting at Ramp
ECS Texas, LLP
WO:64283
* B to P - Batch to Placement time in minutes