MEETING MINUTES
Page 1
Weekday: Wednesday Date: 09-07-2016 Time of Meeting: 08:30 AM Project No.: CPL14141
Project Name:
Denton Tap/ Sandy Lake Streetscape
Improvements Subject: Weekly Construction Coordination Meeting
PRESENT AT MEETING:
City of Coppell
JE - John Elias
MM-Marcus Marion
KP-Kevin Price
AALC
TB-Travis Baird
Teague Nall and Perkins
GP- Guy Pokhrel, P.E.
JM- Joe Madrid
Pavecon
MB- Michael Beattie
DISTRIBUTION:
All Attendees and George Marshall
PREPARED BY: GP DATE OF REPORT: 09-26-2016
The following summation represents our interpretation of the items discussed at the referenced meeting. Any persons desiring to comment on or correct the minutes are
requested to put their comment in writing to Teague Nall and Perkins, Inc. within 10 days of the date of the report. Otherwise the minutes will stand as written.
PRIOR BUSINESS:
Item Items for Discussion Responsibility Due Date
NEW BUSINESS:
Item Items for Discussion Responsibility Due Date
1
TB and MB provided the status update on construction of landscaping items.
Following are noted:
TB: Sodding started in Denton Tap. One truck load sod delivered
yesterday and another truck load scheduled for Friday.
JM: Revised landscape plans sent out by TNP to clarify for boulder sizes.
JM: Crepe Myrtle plant material looks different (Brown in color) in Denton
Tap north of RR tracks, north of Beltline Road.
MB: Frontier has not marked the lines by Parkway. Currently scheduled for
12th.
TB: TB to hold on sodding until boring is completed in median between
Parkway and Bridge.
TB: AALC to water three times a day for newly sodded area..
MB: Controllers are installed for irrigation. Only 10 gauge wire needed to
be installed for controllers. Water service in Sandy Lake is finishing today.
MB: Pavecon to pour concrete by Bethel first and then complete stamped
concrete in Sandy Lake Road.
N/A N/A
2
Discussion on Monument Sign and Illumination and Oncor Infrastructures. Following
are noted:
MB- MB to submit LED information to City.
MB: Light poles are staked for West Sandy Lake Road. MB and George
to examine the location of light poles.
No update on walkthrough meeting with Oncor for final acceptance.
N/A N/A.