meeting notes 02-28-03 final
MEMORANDUM
To: Ken Griffin, P.E.-City of Coppell
From: Jay Volk
Date: March 3, 2003
Re: West Sandy Lake Road Project – 02/27/03 Meeting Notes
NOTE: FOLLOW-UP NOTES FROM THE MEETING
ARE IN RED AND ITALICS.
ATTENDANCE: Ken Griffin, P.E., Dir. of Engineering & Public Works – City of Coppell
Suzan Taylor, C.I.P. Coordinator – City of Coppell
Mike Jones, P.E.
– TNP Fort Worth Office
Jay Volk, P.E. – TNP Dallas Office
Mark Holliday, P.E. – TNP Dallas Office
Matt Atkins, Graduate Engineer – TNP Dallas Office
Meeting w/ City of Coppell
Friday,
February 28, 2003
Update Design Schedule
Phase 1 – (Project ST 99-02 A) State Highway 121 to State Road
Construction is anticipated to start in mid 2004 according to the City’s website.
Still current.
Complete Preliminary Design – August 1, 2003 Okay
Complete City Review – September 1, 2003 Okay
Complete Final Design – December 1, 2003 Okay
Begin R/W Acquisition
– October 1, 2003
The City would like to begin acquisition as soon as possible for Phase 1, since it may take a year. Phase 2 will be addressed later. The City provided TNP with a
copy of the final plat for Amberpoint showing dedication along Sandy Lake Road and State Road.
Begin Utility Relocations – January 1, 2004
Schedule as shown is acceptable.
Phase 2 –
(Project ST 99-02 B) State Road to Denton Tap Road
Construction is anticipated to start in mid 2007 according to the City’s website The schedule for Phase 2 could possibly be delayed further depending on future budget restraints
Complete
Preliminary Design
Complete City Review
Complete Final Design
Begin R/W Acquisition
Begin Utility Relocations
Schedule for Phase 2 to be developed later.
Public Meeting
Date/Location
Information/Exh
ibits
Format
Additional funding from Dallas County is being sought by the City and if approved public hearings will be necessary. Also, the City may hold their own “neighborhood meetings”
for Phase 1 and/or Phase 2.
Discussion of Schematic Design Report and Plans – Phase 1 Issues
Proposed Roadway Section: 6-Lane Divided; minimum r/w width-110 feet
Phase 1 will consist
of the design and construction of the outside four-lanes of an ultimate six-lane divided roadway, instead of the full six-lane section. The proposed median width for Phase 1 will be
40-feet to accommodate the future construction of one additional lane in each direction. Storm drainage facilities will be designed for the ultimate six lanes of pavement.
Left turn
lanes need to be 11-feet wide. The schematic plans showed this width to be 10-feet.
Proposed Pavement Section: 8-inch reinforced concrete pavement/8-inch lime stabilized subgrade.
Lime application rate should be 42#/SY (min.); reinforcing should be the City’s standard of #3 bars at 24” O.C.E.W.
Horizontal Alignment
Super-elevation/design speed - Coppell Road
North The City and TNP discussed the super-elevation at Coppell Road North, but never developed a clear consensus about whether or not the design speed was acceptable. Some discussion
focused on the City’s interest in the possibility of raising the roadway grade in this area, however, the existing retaining wall on the north side of the roadway (east of Coppell Road
North) may prevent this from being practical. The City will provide existing plans for the retaining wall to TNP for evaluation. TNP will then look at options, if any, for the horizontal
and vertical alignment in this area and discuss them again with the City.
w/super-elevation: 40-42 mph
w/o: 35-37 mph
Limits of improvements (west end and east end). The west limits
shall be as shown on the schematic plans. The east end limits will be immediately east of Coppell Road North at an appropriate transition
point. Roadway and drainage improvements may not terminate at the same location.
Status of MIS for State Highway 121 - Still in EA review.
Proximity to north R/W line & TXU Overhead
Transmission Towers – OK, but TNP to look at the impact of proposed cut (and/or fill) on the TXU tower foundations and discuss with TXU to determine if they will have any concerns.
Transition
from 6-lanes to 4-lanes and vice-versa – Concept is OK but TNP to evaluate and revise transition based upon the proposed design of only the outside 4-lanes west of Freeport Parkway (State
Road).
Vertical Alignment
TNP to check cut/fill slopes in cross-sections. Minimum slope shall be 4:1. City will obtain slope easements or permission to grade, as necessary.
See notes
under IIIc(i)1 above.
Signalization
Royal Lane? Yes.
State Road? Not likely to need traffic signalization with this project. Design will provide for conduit only.
Coppell Road North?
Yes
Survey of Outfall Drainage (north of W. Sandy Lake Road) TNP advised City of inability to obtain permission to get access to some properties for survey. City will contact property
owners to get permission.
Royal Lane
Include construction of southbound lanes and divided median?
Yes.
Median width shall be 36.5’ as shown in our plans.
Sidewalk Construction?
Sidewalk
will not be shown along the north side of the roadway, west of Freeport Parkway.
Sidewalk on the south side should be set back from curb at least 2-feet, where possible. Any sidewalks
adjacent to back of curb need to be 6-feet in width.
Sidewalks should not overlap inlet tops.
The City wants the proposed hike/bike trail to be extended from Coppell Road North to Freeport
Parkway and south on Freeport Parkway. The City would prefer the trail to be designed and constructed on the north side of the roadway in this area, but that may not be possible because
of limited R/W and TXU transmission towers.
The City would prefer that the proposed hike/bike trail to the east of Coppell Road North, along the south side of the roadway, be moved away
from the back of curb by at least 3 feet. The trail width could be reduced from 10 feet to 8 feet, if necessary, to help facilitate this adjustment.
The roadway trail crossing at Coppell
Road North needs further evaluation and discussion to make sure that it is not impeded by vehicles that are stopped at the intersection.
There may be some issues related to the proposed trail alignment where it is shown outside of the proposed or existing R/W. Some of these areas are controlled by the HOAs, not the City.
TNP
to schedule a meeting in the near future with NJB and the City to discuss the trail extension, the trail alignment, roadway crossings and other issues related to the proposed sidewalk
and trail systems.
Other City Review Comments
The City’s review comments will be evaluated and addressed by TNP and a detailed response provided to the City at a later date. The City
provided a written list of comments dated March 27, 2002.
The City provided a mark-up set with additional comments.
TNP to Confirm that drainage areas are consistent with proposed improvements
in areas of superelevation.
Refer to city comments and mark-up for additional left turn lane and drive approach needs. The City’s review comments will be evaluated and addressed by
TNP and a detailed response provided to the City at a later date.
Discussion of Schematic Design Report and Plans – Phase 2 Issues
Proposed Roadway Section: 4-Lane Divided; minimum
r/w width-90 feet Left turn lanes need to be 11-feet wide. The schematic plans showed this width to be 10-feet.
Proposed Pavement Section: 8-inch reinforced concrete pavement/8-inch
lime stabilized subgrade. Lime application rate should be 42#/SY (min.); reinforcing should be the City’s standard of #3 bars at 24” O.C.E.W.
Horizontal Alignment
Super-elevation/design
speed - Coppell Road South The City and TNP discussed very briefly the super-elevation at Coppell Road South, but never developed a clear consensus about whether or not the design speed
was acceptable. TNP and City will need to re-visit this issue before proceeding with the preliminary design of Phase 2.
w/super-elevation: 45-47 mph
w/o: 40-42 mph
Conflict w/TXU Transmission
Poles. The City acknowledged that up to four poles would need to be relocated.
Tree Preservation/Removal
4-Lane Divided vs. 4-Lane Undivided. The City prefers that the 4-lane divided
alternative be designed and constructed. A final decision will be needed from the City before TNP proceeds with preliminary design of Phase 2.
Bridge conflict w/ 24-Inch Water Line.
This item was not addressed at the meeting.
Vertical Alignment
Retaining Walls TNP to clarify the maximum wall height required. The schematic report indicates that the maximum is 11
feet, however, the plans show the maximum height to be only 8 feet.
24-Inch Water Line Adjustment This item was not discussed at the meeting.