RE: Sandy Lake Road Project attachments to PSA (4)Keith,
Attached is the PSA for the Sandy Lake Road Project. I did not include
the $99,092.01, since cost is still incurring. If you have any
questions, please feel free to contact me.
Sherri Turner
From: Keith Marvin [mailto:KMarvin@coppelltx.gov]
Sent: Wednesday, May 21, 2014 10:58 AM
To: John Mears
Cc: Sherri Turner; Belinda Hayward; Kenneth Griffin; Melody Davis
Subject: RE: Sandy Lake Road Project attachments to PSA
John,
The original contract amount for the Phase B project was $8,633,084.52.
We have approved two change orders for an additional $99,092.01.
I’m out of the office right now, but if you need the bid tabulation,
let me know and I’ll get it sent over to you.
Keith
From: John Mears [mailto:John.Mears@dallascounty.org]
Sent: Wednesday, May 21, 2014 10:01 AM
To: Keith Marvin
Cc: Sherri Turner; Belinda Hayward; Melody Davis
Subject: RE: Sandy Lake Road Project attachments to PSA
Keith, we are going to get this PSA to you shortly.
I think the numbers we have are for the overall project. We have been
asked to get an approximate total budget number for the Phase B section.
If we can get that number we should be good to go.
Thank you.
John
________________________________
From: Keith Marvin [KMarvin@coppelltx.gov]
Sent: Tuesday, May 13, 2014 3:31 PM
To: John Mears; Belinda Hayward
Cc: Alberta Blair; Kenneth Griffin; Sherri Turner; Melody Davis
Subject: RE: Sandy Lake Road Project attachments to PSA
John,
The current contract time will run out in August. We are experiencing
delays associated with franchise utilities that may impact the final
completion date.
Keith Marvin, P.E.
Assistant Director of Public Works
Engineering Department
City of Coppell, TX
www.coppelltx.gov <http://www.coppelltx.gov>
972-304-3681 (office)
<http://www.coppelltx.gov/>
<https://www.facebook.com/pages/City-of-Coppell-TX-Municipal-Government/
324357528624> <https://twitter.com/CityofCoppell>
<http://www.youtube.com/CityOfCoppellTX>
<http://www.coppelltx.gov/ecocoppell-522.html>
Please take our customer service survey
<https://owa.dallascounty.org/owa/UrlBlockedError.aspx>
From: John Mears [mailto:John.Mears@dallascounty.org]
Sent: Tuesday, May 13, 2014 2:14 PM
To: Keith Marvin; Belinda Hayward
Cc: Alberta Blair; Kenneth Griffin; Sherri Turner; Melody Davis
Subject: RE: Sandy Lake Road Project attachments to PSA
We have construction scheduled to be complete in August for the
agreement. Is that still good or does it need to be updated?
John