WA9302-CS 951227SHIMEK, JACOBS & FINKLEA CONSTRUCTION REPORT 'rojectNo. 94155 Date: 12-27-95 Prepared Is This A By: Matt Hickey ~-~ Working Day? [] Yes [] No Owner: City of Coppell Project Name: Village Parkway Ground Storage Reservoir No. 2 Construction Contractor: NATGUN Time Allotted: 300 Used: 164 Number Superintendent: Jim Fisher Men Working: 18 Hours: 9:00 AM to 9:25 AM Weather Conditions: Clear and Cold Site Conditions: The site was well maintained. WORK DESCRIPTION 1. Twenty dome panels have been poured. Twenty additional dome panels are expected to be poured on January 2, 1996. 2. Four wall panels are expected to be poured on January 2, 1996. 3. Scaffolding for the dome panels are being erected on the tank floor. 4. The standing water on the driveway near the office is being pumped to the concrete channel along Kimbel Kourt.