Copperstone-CS 960416BriscoeClark
April 16, 1996
Mr. Ken Griffin
City of Coppell
255 Parkway Blvd.
P.O. Box 478
Coppell, Texas 75019
Re: Copperstone Addition, Final Inspection and Acceptance of Paving and Utility
Improvements
Dear Ken:
The Utility and Paving Improvements for the Copperstone Addition are completed except
for the Bridge over Cottonwood Creek and a small amount of related paving. It is our
request that we treat these as separate jobs and final out the subdivision improvements
now. We would then final the bridge and related pavement at a future date. By finaling the
subdivision improvements now we will be able to start the construction of the franchise
utilities immediately and it will also allow us get the homebuilders started on their model
homes. The subdivision has good access from Parkway Blvd. to the West, which will
provide for adequate fire protection until the bridge is complete.
This is a schedule of the remaining improvements and their estimated completion times:
Parkway Blvd. Bridge - 30-45 days
Screening Walls and Entryway Treatments - 45-60 days
Parkway Blvd. Landscaping - 60 days
Pond Retaining Wall, Grading and Landscaping - 60 days
Park Access and Fencing - 60 days
We appreciate your help on this matter. If you should have any questions or need
additional information please do not hesitate to contact me.
James P. Briscoe
Partner