WA9302-CS 951227 (2)SHIMEK, JACOBS & FINKLEA CONSTRUCTION REPORT Project No. 94155 Date: 12-27-95 Prepared ~ Is This A By: Matt Hiekey Working Day? [] Yes [] No Owner: City of Coppell Project Name: Village Parkway Ground Storage Reservoir No. 2 Construction Contractor: NATGUN Time Allotted: 300 Used: 158 Number Superintendent: Jim Fisher Men Working: 20 Hours: 9:00 AM to 9:25 PM Weather Conditions: Clear and Cold Site Conditions: The site was well maintained. WORK DESCRIPTION 1. Casting beds for the wall and dome panels were being constructed. Dome panels are scheduled to start being poured on December 28, 1995. 2. The tank slab will remain flooded until the wall and dome panels are in place. 3. Scaffolding is being delivered to the job site. 4. The existing tank overflowed and standing water is on the driveway near the office.