From:Matthew Mabry
Sent:Tuesday, February 07, 2017 3:16 PM
To:Jim Smith
Cc:Dilip Pranav
Subject:Re: FFIS Coppell
Yes that is correct per our standard construction details.
Sent from my iPhone
On Feb 7, 2017, at 1:42 PM, Jim Smith <jsmith@northpointconst.com> wrote:
Matt,
As per our conversation regarding the thickness of the concrete in the fire lane you said that if we didn’t
lime stabilize we were to make the thickness 8”. Is this correct??
Should you have any questions or concerns please call me.
Thank you,
Jim Smith
Asst. Project Manager
Northpoint Construction
469 515 3027
jsmith@northpointconst.com