Fairfield-CS170207 Halie Hernandez From:Matthew Mabry Sent:Tuesday, February 07, 2017 3:16 PM To:Jim Smith Cc:Dilip Pranav Subject:Re: FFIS Coppell Yes that is correct per our standard construction details. Sent from my iPhone On Feb 7, 2017, at 1:42 PM, Jim Smith <jsmith@northpointconst.com> wrote: Matt, As per our conversation regarding the thickness of the concrete in the fire lane you said that if we didn’t lime stabilize we were to make the thickness 8”. Is this correct?? Should you have any questions or concerns please call me. Thank you, Jim Smith Asst. Project Manager Northpoint Construction 469 515 3027 jsmith@northpointconst.com 1