Old Town Phase 4-CR170224 Halie Hernandez From:Matthew Mabry Sent:Friday, February 24, 2017 7:52 AM To:Halie Hernandez Subject:Main street phase IV daily report??? Does this work better for you Categories:This message has been archived by Retain on February 25 2017 17:31 PROJECT Main Street phase IV PROJECT NO. OWNER CITY of COPPELL CONTRACTOR Pavecon PROJECT INSPECTOR Matthew Mabry DAILY CONSTRUCTION REPORT DATE ________2/24/2017_____________ REPORT #________________ DAY M T W T F S S WEATHER TEMP WIND HUMIDITY AVERAGE FIELD FORCE NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS VISITORS TIME REPRESENTATIVE REPRESENTING REMARKS 1 EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: Received utility submittals this morning as well as the trench safety plan. They plan to install their SWPPP next week and begin work on 3/1/17 SIGNATURE PUBLIC WORKS INSPECTOR Matthew Mabry Engineering Construction Inspector City of Coppell, TX 214-406-5223 (cell) www.coppelltx.gov 2