Prologis Park-DR022017 DAILY CONSTRUCTION REPORT DATE _____________________ REPORT #________________ PROJECT Prologis Building 3 DAY M T W T F S S PROJECT NO. WEATHER Sunny OWNER CITY of COPPELL TEMP 81 WIND S 11 MPH CONTRACTOR Mycon HUMIDITY 37 PROJECT INSPECTOR Marcus Marion AVERAGE FIELD FORCE NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS VISITORS TIME REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: Mycon is hanging steel on the building pad Potter is wrecking and building forms for the walls that they plan to pour on Friday Steel was delivered on site today for the buillding SIGNATURE PUBLIC WORKS INSPECTOR Page _____ of _____ pages. DAILY CONSTRUCTION REPORT REPORT #_____________ Page _____ of _____ pages.