Prologis Park-DR170224 DAILY CONSTRUCTION REPORT DATE __02/24/2017___________ REPORT #________________ PROJECT: Prologis Building 3 DAY M T W T F S S PROJECT NO. WEATHER Sunny OWNER Prologis TEMP 59 WIND NW 15 MPH CONTRACTOR: Mycon 40 HUMIDITY PROJECT INSPECTOR: Marcus Marion AVERAGE FIELD FORCE NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS VISITORS TIME REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: Mycon is still hanging steel on the building pad Potter is still working on the installing steel and forming of wall panels Potter is prepping for the next pour I was informed that Cal made the repair to the broken water line SIGNATURE PUBLIC WORKS INSPECTOR Page _____ of _____ pages. DAILY CONSTRUCTION REPORT REPORT #_____________ Page _____ of _____ pages.