Prologis Park 121 Northwest Dr--DR170224
DAILY CONSTRUCTION REPORT
DATE __02/24/2017___________ REPORT #________________
PROJECT: Northwest Dr.
DAY
M T W T F S S
PROJECT NO.
WEATHER Sunny
OWNER CITY of COPPELL
TEMP 57
WIND NW 15
CONTRACTOR: Mycon
40
HUMIDITY
PROJECT INSPECTOR: Marcus Marion
AVERAGE FIELD FORCE
NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS
VISITORS
TIME REPRESENTATIVE REPRESENTING REMARKS
EQUIPMENT AT THE SITE:
CONSTRUCTION ACTIVITIES:
Still waiting on the rest of the test from the sewer lines and the manholes
The 10” thick concrete will be allowed at the intersection of Northwest Dr. and Subaru
Earth Basics will be onsite next week to start grading
SIGNATURE
PUBLIC WORKS INSPECTOR