Freeport NIP(3)-CS 950602The City With A Beautiful Future
P.O. Box 478
Coppell, Texas 75019
214-462-0022
June 2, 1995
Mr. Ab Atkins
MEPC American Properties Inc.
15303 Dallas Parkway
Suite 100 LB 10
Dallas, Texas 75248
RE: MEPC American Properties / Freeport North Lot 3R,
Development Fee Assessment
Dear Mr. Atkins:
Enclosed is a copy of the City of Coppell Development Fee Assessment list, along with a copy of
the Development Fee Calculations for Freeport North Lot 3R.
Please make payment to the City of Coppell in the amount of $11,925.00 and forward it to Alan
Johnson, Finance Director, along with a copy of the Fee Assessment List. A copy of the Engineer's
estimate or contract for this project will need to be provided to our department so the construction
inspection fee can be verified.
Providing a copy of your paid receipt to our office will help us to verify payment of the required
fees and insure a successful beginning of this project. We look forward to working with you on this
project. If you have any questions, please do not hesitate to contact me.
Sincerely,
Kenneth M. Griffin, P.E.
Asst. City Manager/City Engineer
CC:
Alan Johnson, Finance Director
Greg Jones, Building Official
Doug Stevens, Engineering Technician
Howard Pafford, Utilities Superintendent
Rey Gonzales, Street Superintendent
Rick Wieland, Parks and Recreation Manager
CITY OF, COPPELL
DEVELOPMENT FEES
Date:
Project:
May 31, 1995
MEPC American Properties/Freeport North Lot 3R
TOTAL AMOUNT DUE
FEES DUE PRIOR TO
COUNCIL
APPROVAL
Water Impact Fee $8,325.00 $8,325.00
(100% due prior to Council Approval)
Water Tap Inspection Fee $300.00 -0-
(100% due at Issuance of Water Meter)
Wastewater Impact Fee $3,600.00 $3,600.00
(100% due prior to Council Approval)
Sewer Tap Inspection Fee -0- -0-
(100% due at Issuance of Building Permit)
Utility Final Inspection Fee $50.00 -0-
(100% due at Issuance of Building Permit)
Water Meter Fee (Domestic) $173.65 -0-
(100% due at Issuance of Water Meter)
Water Meter Deposit $70.00 -0-
(100% due at Issuance of Water Meters)
Water Meter Deposit (Residential) -0- -0-
(100% due at Issuance of Building Permit)
Water Meter Fee (Irrigation & Fire) $2,551.85 -0-
(100% due at Issuance of Water Meters)
Irrigation Meter Deposit $35.00 -0-
(100% due at Issuance of Water Meters)
Street Sign Fee -0- -0-
(100% due prior to Acceptance of Project)
Street Light Fee * information not -0-
(100% due prior to Acceptance of Project) available
Park Fee -0- -0-
Street Excrow -0- -0-
(100% due prior to Council Approval)
Construction Inspection Fee need submittal of -0-
(2 % of Project Cost due prior to Preconstr. Mtg.) contracts
TOTAL $15,105.50
TOTAL AMOUNT DUE PRIOR TO COUNCIL APPROVAL $11,925.00
* This fee cannot be assessed until after TU Electric submits the lighting plan for the proposed project. Once the plan
is submitted, $292.60 per light will be assessed.
COPPELLENGINEERING
MEMORANDUM
DATE: May 26, 1995
TO: Mike Martin, E.I.T.
FROM: Howard Pafford, Utilities Superintendent
RE: Development Fees for MEPC American
The following fees should be assessed and collected on the above
referenced project.
Water Impact Fee:
1 - 2" Domestic Meter/s = 8 ESU's
1 - 2" Irrigation Meter/s = 8 ESU's
1 - 8" Fireline Meter/s = 2.5 ESU's
Total 18.5
ESU's ~ $450.00 ea = $ 8,325.00
100% due prior to Council approval of the final plat.
Wastewater Impact
1 - 2" Domestic Meter/s = 8 ESU's
Total 8 ESU's @ $450.00 ea = $3,600.00
100% due prior to Council approval of the final plat.
Water Tap Inspection Fee
3 Connections ~ $100.00 each = $~00.00
100% due prior to issuance of building permit for residential. (Or in
the case of multi-family, commercial, retail, industrial, fee is due
prior to issuance of meter).
Utility Final Inspection Fee (All Development)
1 lots @ $ 50.O0/lot = $50.00
100% due prior to issuance of building permit.
Development Fees
Page 2
Water Meter Fee (Domestic)
1 - 2" Domestic Meters @ $173.65ea. = $173.65
100% due prior to issuance of building permit for residential only.
Ail other development fees are due prior to issuance of meter/s.
Water Meter Fee (Irrigation/Fireline)
1 - 2" Irrigation Meter/s @ $173.65 ea = $173.65
1 - 8" Fireline Meter/s ~ $ 2,378.20 ea = $2,378.20
100% due prior to issuance of water meter/s.
Water Meter Deposit (Multi-F-mily or Non-Residential)
2 Meters ~ $35.00 ea = $70.00
100% due prior to issuance of water meters.
Irrigation Meter Deposit
1 Meters ~ $35.00 ea = $35.00
100% due prior to issuance of water meters.
ESCROW / ROADWAY IMPACT FEE CALCULATIONS
PROJECT:
DATE:
MEPC American Properties / Freeport North Lot 3R
6/5/95
STREET ESCROW:
Street Name(s)
Royal Lane
P4D/6
Street T}q~e
Cost per Foot $0.00 ***
Length of Adjacent Frontage (Linear Feet) 0
Escrow due = (Cost per Foot) x (Length of Adjacent Frontage) = $0.00
ROADWAY IMPACT FEE:
Service Area * '4
Category ** Industrial
Land Use**
Building Size (Sq. Ft.)
Development Units **
Vehicle Miles per Development Unit **
Fee per Vehicle Mile
General Light Industrial
368,000
368
$300
Roadway Impact Fee due = (Development Units) x
Vehicle Miles Per Development Unit) x (Fee Per Vehicle Mile) = $117,024.00
* (Figure 2 - Roadway Impact Fee Study)
** (Table 3 - Roadway Impact Fee Study)
*** (Road has been upgraded)
Amount due is the lesser of the Street Escrow or the Roadway Impact Fee.