Prologis Park 121 Northwest Dr--DR170306 DAILY CONSTRUCTION REPORT DATE ___03/06/2017__03:10pm_ REPORT #________________ PROJECT: Northwest Dr. DAY M T W T F S S PROJECT NO. WEATHER Mostly Cloudy OWNER CITY of COPPELL TEMP 75 CONTRACTOR: CORE WIND S 25 HUMIDITY 53 PROJECT INSPECTOR: Marcus Marion AVERAGE FIELD FORCE NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS VISITORS TIME REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: CalHar is completing the tie-in for the 8” water line Northwest Dr. South I reminded Chance from Mycon that I still need the sewer line low pressure test and the mandrel and vacuum test before the pavement gets put in. Even though the storm inlet is TxDOT, I still need to look at the tie-in of our line. SIGNATURE PUBLIC WORKS INSPECTOR Page _____ of _____ pages. DAILY CONSTRUCTION REPORT REPORT #_____________ Page _____ of _____ pages.