Prologis Park 121 Northwest Dr--DR170306
DAILY CONSTRUCTION REPORT
DATE ___03/06/2017__03:10pm_ REPORT #________________
PROJECT: Northwest Dr.
DAY
M T W T F S S
PROJECT NO.
WEATHER Mostly
Cloudy
OWNER CITY of COPPELL
TEMP 75
CONTRACTOR: CORE
WIND S 25
HUMIDITY 53
PROJECT INSPECTOR: Marcus Marion
AVERAGE FIELD FORCE
NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS
VISITORS
TIME REPRESENTATIVE REPRESENTING REMARKS
EQUIPMENT AT THE SITE:
CONSTRUCTION ACTIVITIES:
CalHar is completing the tie-in for the 8” water line Northwest Dr. South
I reminded Chance from Mycon that I still need the sewer line low pressure test and the mandrel and vacuum test before the pavement gets put in.
Even though the storm inlet is TxDOT, I still need to look at the tie-in of our line.
SIGNATURE
PUBLIC WORKS INSPECTOR
Page _____ of _____ pages.
DAILY CONSTRUCTION REPORT
REPORT #_____________
Page _____ of _____ pages.