Prologis Park 121 Northwest Dr--DR170307
DAILY CONSTRUCTION REPORT
DATE ___03/07/2017__03:10pm_ REPORT #________________
PROJECT: Northwest Dr.
DAY
M T W T F S S
PROJECT NO.
WEATHER Mostly
Cloudy
OWNER CITY of COPPELL
TEMP 63
CONTRACTOR: CORE
WIND NNE 13
HUMIDITY 79
PROJECT INSPECTOR: Marcus Marion
AVERAGE FIELD FORCE
NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS
VISITORS
TIME REPRESENTATIVE REPRESENTING REMARKS
EQUIPMENT AT THE SITE:
CONSTRUCTION ACTIVITIES:
The contractor is working on pre-presuring the water line for the hydrostatic test on Wednesday
The water line is connected and both valves are opened back up.
I informed Mycon that the storm drain belonged to TxDOT.
SIGNATURE
PUBLIC WORKS INSPECTOR
Page _____ of _____ pages.