Loading...
Wrangler Olympus-CR170227 Halie Hernandez From:Matthew Mabry Sent:Tuesday, February 28, 2017 8:13 AM To:Halie Hernandez Subject:Wrangler Beltline signal daily report Categories:This message has been archived by Retain on February 28 2017 17:41 PROJECT Wrangler/Beltline signal PROJECT NO. OWNER CITY of COPPELL CONTRACTOR Lacy PROJECT INSPECTOR Matthew Mabry DAILY CONSTRUCTION REPORT DATE 2-27-2017 REPORT #1 DAY M T W T F S S Weather: Temp: Humidity: Wind: AVERAGE FIELD FORCE NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS VISITORS TIME REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT THE SITE: 1 CONSTRUCTION ACTIVITIES: Cody Wildoner and I met with paving, developer, and signal contractor on site to discuss drainage issues and the existing signal wires that are in the way. I told the contractor and developer that I would send them the original plans for Belt line road to answer any of their questions about the current drainage and inlets that do not show up on GIS SIGNATURE PUBLIC WORKS INSPECTOR: MATTHEW MABRY Matthew Mabry Engineering Construction Inspector City of Coppell, TX 214-406-5223 (cell) www.coppelltx.gov 2