Prologis Park-CR170224
Halie Hernandez
From:Matthew Mabry
Sent:Friday, February 24, 2017 1:58 PM
To:Halie Hernandez
Subject:Prologis Building 6 daily report
Categories:This message has been archived by Retain on February 25 2017 17:30
PROJECT Porlogis Building 6
PROJECT NO.
OWNER CITY of COPPELL
CONTRACTOR MYCON
PROJECT INSPECTOR Matthew Mabry
DAILY CONSTRUCTION REPORT
DATE 2-24-2017 REPORT #1
DAY M T W T F S S
Weather:
Temp:
Humidity:
Wind:
AVERAGE FIELD FORCE
NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS
VISITORS
TIME REPRESENTATIVE REPRESENTING REMARKS
1
EQUIPMENT AT THE SITE:
CONSTRUCTION ACTIVITIES:
Waiting on pavecon to finish Northwest drive to finish fire lane so they can go vertical on the building.
SIGNATURE
PUBLIC WORKS INSPECTOR: MATTHEW MABRY
Matthew Mabry
Engineering Construction Inspector
City of Coppell, TX
214-406-5223 (cell)
www.coppelltx.gov
2