Park West Crossing-CR170303
Halie Hernandez
From:Matthew Mabry
Sent:Monday, March 06, 2017 7:49 AM
To:Halie Hernandez
Subject:Parkwest phase II daily report
Categories:This message has been archived by Retain on March 06 2017 17:41
PROJECT Parkwest phase II
PROJECT NO.
OWNER CITY of COPPELL
CONTRACTOR Structure tone
PROJECT INSPECTOR Matthew Mabry
DAILY CONSTRUCTION REPORT
DATE 3-3-2017 REPORT #1
DAY M T W T F S S
Weather:
Temp:
Humidity:
Wind:
AVERAGE FIELD FORCE
NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS
VISITORS
TIME REPRESENTATIVE REPRESENTING REMARKS
EQUIPMENT AT THE SITE:
1
CONSTRUCTION ACTIVITIES:
Still finishing up on landscaping. Received their ADA inspection I am only waiting on paving bonds to issue the final acceptance letter.
SIGNATURE
PUBLIC WORKS INSPECTOR: MATTHEW MABRY
Matthew Mabry
Engineering Construction Inspector
City of Coppell, TX
214-406-5223 (cell)
www.coppelltx.gov
2